目录1. 主要编制依据....................................................2.1标准层办公区................................................................................................................................2.2标准层走廊....................................................................................................................................3.1主要机具及劳动力投入...............................................................................................................3.2施工工期........................................................................................................................................3.3施工条件........................................................................................................................................4.1材料质量要求................................................................................................................................4.2材料准备........................................................................................................................................4.3材料进场要求................................................................................................................................4.3.1材料装卸........................................................................................................................................4.3.2材料搬运........................................................................................................................................4.3.3材料码放及标志............................................................................................................................4.4技术准备........................................................................................................................................5.1施工工艺流程................................................................................................................................5.2场地清理........................................................................................................................................5.3按照图纸设计弹线 .......................................................................................................................5.4不平整地面的处理 .......................................................................................................................5.5安装竖向支架................................................................................................................................5.6固定支架........................................................................................................................................5.7铺设地板........................................................................................................................................6.1主控项目........................................................................................................................................6.2一般项目........................................................................................................................................6.3国家规范要求及标准...................................................................................................................8.1运输和保存注意事项...................................................................................................................8.2安全文明施工保证措施...............................................................................................................8.3雨季施工技术措施 .......................................................................................................................1. 主要编制依据●《建筑地面工程施工及验收规范》(GB50209-2002)●《建筑装饰装修工程质量验收规程》(GB50210-2001)●《建筑工程施工质量验收统一标准》(GBJ50300-2001)●《人造板及饰面人造板理化性能试验方法》(GB/T17657-1999)●《室内装饰装修材料聚氯乙烯卷材地板中有害物质限量》(GB18586-2001)●《建筑安装分项工程施工工艺规程》(DBJ01-26-96)●《北京市建筑工程施工现场安全管理标准》(DBJ01-62-2002)●《中国石油大厦施工组织设计》(CL4/A138/C/2002)●中国石油大厦架空地板深化设计图纸2. 工程概况●中国石油大厦是北京华昌置业有限公司投资兴建,由北京建筑设计研究院负责设计,中建一局建设发展公司总承包的大型公建项目。
大厦位于北京市东城区二环交通商务区北部,东二环北段西侧,东直门桥西北,与东直门交通枢纽相对,建成后将作为中国石油天然气集团公司总部办公大楼。
●中国石油大厦建筑群,由基础相连的A、B、C、D四栋塔楼组成,九层以下的裙房通过三个超大型中庭联成一体。
2.1标准层办公区●架空地板高度为72mm,地毯(7mm)和粘结剂(1mm)厚度,装修面层实际最终完成高度为80mm。
2.2标准层走廊●走廊是规则矩形,架空地板铺设到墙体饰面材料下部(如石材、木挂板等)。
●架空地板高度同标准层办公区,面层完成高度为72mm。
3.施工安排3.1主要机具及劳动力投入A、B、C楼机具投入:A、B、C楼劳动力投入:D楼机具投入:D楼劳动力投入:3.2施工工期●本工程施工时间拟于2007年7月中旬开工,2007年10月中旬结束。
具体时间以项目经理部的施工进度计划为准。
3.3施工条件●施工条件:①机电线槽安装完毕;②楼地板清理干净、无垃圾;③吊顶主要施工内容已经完毕。
4.施工准备4.1材料质量要求●架空地板、支架等材料应符合设计要求及GB50209-2002《建筑地面工程施工及验收规范》4.2材料准备网络架空地板系统组成4.3材料进场要求4.3.1材料装卸●架空地板材料装卸进入工程所指定的位置时,支架和板块要整齐地放在指定区域,支架及板块不能有变形。