2.3标记开槽位置 Mark the grooving line
线管开槽控制线要求:线管间距≧10mm、线管与砌体墙间距≧10mm,开槽控 制线宽度=线管外径+线管间距+线管距墙间距,开槽控制线布置清晰合理;严禁 水平开槽,如必须水平开槽的,水平开槽长度不得大于300mm。
Requirements for mark conduit grooving control line: between conduit&conduit minimum is 10mm, between conduit&grooving side minimum is 10mm, groove wide control line width =dia of conduit+
wide(between conduit&conduit)+ wide( between conduit&grooving side) ,and groove control line layout shoule be clear .Horizontal grooving is strictly prohibited, If horizontal grooving is necessary, the length of horizontal grooving shall not be greater than 300mm.
标记开槽位置 Mark the grooving line
2.4开槽 Grooving
开槽必须采用专用开槽机开槽,严禁采用电锤或人工开槽,线槽开槽深度=线 管外径+15mm。
量取标高控制线做标记 Measure the elevation control line to mark
标记线盒高度位置 Mark the electric box elevation
常用开关插座灯具安装高度 common switch 、socket &light altitued
名称(Name) 插座socket outlet
开关switchtrobe light 紧急呼叫按钮Emergency call button
电铃(bell)
安装高度(Altitued ) 0.3m 1.3m
门上0.2m(0.2 m above door )
0.5m
0.6m
2.5m
其余此处未提及详见图纸 For the other which not mention, please refer to the drawing
1.2主要施工机具及测量工具 Machine&tools prepration 1.机械:开槽机、切割机 2.工具:弯管器、锯弓、锯条、记号笔、锉刀、锤子、水平尺、角尺、卷尺、 灰桶、灰铲、脚手架等。
1. Machine: slot machine, cutting machine 2. Tools: pipe bender , bow saw, saw blade, marking pen, file, hammer, leveling ruler, Angle ruler, tape measure, ash barrel, ash shovel, scaffolding, etc.
电气开槽配管(JDG)
grooving&conduit installation Training
目 录 Catalogue
一、施工准备 二、操作工艺 三、质量控制 四、安全文明施工
Preparation Method of operation Quality control Safety construction
一、施工准备 Preparation
1.1材料要求 Material required
1.线管及其配件,安装前应进行外观检查,型号、规格符合设计要求, 2.导管外壁镀层均匀、完好。 3.管材管口应光滑,若不光滑,需进行打磨处理。 1. The conduit and its accessories shall be inspected before installation, and the type and specification should the same as design requirements. 2. The outer wall of the conduit shoule be smooth and full. 3. The terminal of conduit should be smooth; if not, it should be polished.
2.2定位 Location 根据线盒标高控制线,画出线盒定位线
According to the electric box elevation control line, draw the electric box location
标记线盒位置 Mark the electric box position
二、操作工艺 Method of operation
2.1标高控制 Altitude control 线盒、电箱定位必须严格按照图纸尺寸进行定位,位置必须准确无误,标高 控制,要求必须根据建筑1米线作为基准线,对线盒标高进行弹线定位。
The positioning of the electric box and electric box shall be conducted in strict accordance with the size of the drawing. The position shall be correct, and the altitude control shall be conducted. It is required that the elevation of the electric box shall be located according to the finish level 1-meter line as the baseline.