大门及围墙施工组织设计

工组织设计编制单位:吉林省联合建筑安装有限责任公司编制人:王涛编制时间:二0—二年八月七日第一章工程概况.................................................................. j 第二章编制依据................................................................. 2-第三章施工准备................................................................. 3-第四章主要施工技术jjjjjjjjjjjjjjjjjjjjjjjjjjjj.4j 第一节施工测量............................................................ .£•第二节土方工程jjjjjjjjjjjjjjjjjjjjjjjjjjjj..j8第三节运输及脚手架工程jjjjjjjjjjjjjjjjjjjjjjjj.9j 第四节模板工程jjjjjjjjjjjjjjjjjjjjjjjjjjjj1j1 第五节钢筋、铁件工程jjjjjjjjjjjjjjjjjjjjjjjjj13j 第六节混凝土工程jjjjjjjjjjjjjjjjjjjjjjjjjj .j..1j5 第七节砌体工程jjjjjjjjjjjjjjjjjjjjjjjjjjjj1j7 第八节装修工程jjjjjjjjjjjjjjjjjjjjjjjjjjj..j.1j9 第九节屋面防水工程jjjjjjjjjjjjjjjjjjjjjjjjj .j26j 第五章质量保证体系jjjjjjjjjjjjjjjjjjjjjjjjjjj..j29j 第六章安全施工保证措施jjjjjjjjjjjjjjjjjjjjjjjjj...j30j 第七章文明施工措施jjjjjjjjjjjjjjjjjjjjjjjjjjj..j32j 第八章工期保证措施jjjjjjjjjjjjjjjjjjjjjjjjjjj..j33j 第九章雨季施工措施jjjjjjjjjjjjjjjjjjjjjjjjjjj..j34j 第十章降低工程成本措施jjjjjjjjjjjjjjjjjjjjjjjjj 3j5j附录一选用拟投入的施工机械设备........................................... 36•附录二主要材料需求数量表.................................................... 37 •附录三劳动力计划表. (38)................................................................................................................................. -附录四围墙施工进度计划横道图............................................. :;39附录五门库施工进度计划横道图 (40)附录六保安室施工进度计划横道图........................................... 41 •第一章工程概况1、项目名称: 长春锅炉仪表程控设备股份有限公司大门及围墙2、建设单位: 长春锅炉仪表程控设备股份有限公司3、工程地点: 长春市宽城区北凯旋路4、项目特征: 本项目建设内容有保安室、门库、围墙等工程。

第二章编制依据一、长春锅炉仪表程控设备股份有限公司大门及围墙合同二、施工图纸三、报价预算书四、国家颁布的有关施工标准和规范规程第三章施工准备施工方应作的准备1、劳动力准备:积极办妥本工程所需的一切许可批件手续,组织劳动力进场,选拔配备项目施工精干班子,优选各专业工程的施工力量,为本工程全面施工作施工力量的准备。

2、劳动力计划:为加快施工进度,本工程加大施工劳动力投入,确保按预定工期完工。

3、机械准备:我公司机械设备充足,为保证工程质量和工程进度,我公司将配备先进的施工机械,在进场前对机械操作人员进行分组,确立责、权、利,定编、定岗、定任务,加强安全教育,组织维修人员进场。

进场前,将机械设备全部检修一遍,确保施工时万无一失。

4、施工技术准备:(1)组织施工管理和技术人员熟悉设计文件。

(2)收集有关技术资料,施工规范和操作规程。

(3)了解本工程的水文、地质、气象、岩土等资料。

(4)规划好交通运输路线,做好施工便道、用水、用电及临建布置,做好劳动力、机械、场地和调配计划。

(5)做好详细的施工作业指导书施工组织现场布置、施工程序、施工方法、工程进度计划以及保证质量、安全、进度计划的实施措施。

5、施工场地准备(1)施工现场布置见施工总平面图。

(2)根据现场考察,结合本工程特点,拟在修建区域设基地,主要设施为:办公室、宿舍、职工食堂、钢筋棚、水泥棚。

第四章主要施工技术方案本次施工计划分三班作业,围墙施工班,门牌施工班,保安亭施工班。

三班同时开工,流水作业。

一、门房施工程序本工程遵循先地下后地上,先整体后局部,先主体后装修,先外后内的建设基本程序安排施工。

整个施工过程大体分为± 0.000 以下,主体结构工程、装饰三个阶段,平行流水,主体交叉作业。

1、基础工程放线f机械挖沟槽f人工清理、修整f验槽f浇筑C 10砼垫层—基础放线—轴线复核一钢筋绑扎一模板安装T浇捣砼一养护拆模一回填土2、主体工程施工投点放线f轴线复核f砌筑砖墙f验收构造柱钢筋f支构造柱模板f清理、加固f浇捣砼f 现浇板模板f加固、清理f绑扎现浇板钢筋f验筋f浇捣砼f养护f拆模3、室内装修结构清理f墙面堵跳板眼f做样板间f墙面湿水f贴灰饼冲筋f天棚墙面抹灰f 天棚墙墙面检查验收f楼地面平整打夯-浇捣砼垫层f清理、冲洗f测量做灰饼f楼地面水泥砂浆找平f排砖挂线f 镶贴f擦缝、清洁f内墙面基层清理f内墙混合砂浆粉刷f刮腻子两遍f刮大白一遍f检查验收。

4、室外装修门窗框检查校正f门窗框安装、吊正f墙面结构清理f细石砼堵脚手眼f墙面吊线、放线T墙面水泥砂浆T检查验收T放预埋件线T安装预埋件T焊接主龙骨T焊接次龙骨f安装花岗岩板f填充棒棒条、打耐候胶f检查验收。

二、围墙施工程序投点放线f机械挖沟槽f基础f基础短柱f地梁f砌筑砖柱f安装预制砼压顶f 抹灰f检查验收三、门牌施工程序测量放线f机械挖沟槽f人工清理、修整f验槽f砌毛石基础f浇捣C10砼找平层f砌砖砌体f立模f绑扎压顶钢筋f浇捣砼f养护f拆模f干挂花岗石f安装公司标志牌f检查验收第一节施工测量1 、场地控制网的测设遵守先整体后局部精度控制低精度的工作程序,即先测设场地整体的平面控制网和标高控制网,再以控制网为依据进行建筑物的定位、放线和标高的测设。

本工程测量设置场地控制网,各点的设置优先考虑设置在附近区域内的永久性建筑物墙面上。

如没有永久性建筑,则在场外地面上设置永久性控制桩,控制桩采用砼基座保护处理。

本工程的场地标高控制网共设四个控制点,分别设在建筑物四个角区域附近的永久性控制桩上,并在建筑物本身四个外边柱面设置± 0.000 标高线加以综合控制。

所有设置点均以100mm 三角形用红油漆标绘。

2、测量定位放线本工程根据总平面图中的规划红线,道路中心或甲方移交的测量控制点,采用直角坐标法进行轴线的定位和校核。

为了确保工程质量,防止同测量放线的差错造成的损失,必须在整个施工的各个阶段和各主要部位做好验线工作,并要在审查测量放线方案和指导测量放线工作方面下功夫,改变只是事后验收的被动工作方法。

建立一切定位、放线工作要经自检、互检合格后,方可申请主管部门验收的工作制度。

3、工程轴线控制(1)平面控制本工程建筑物一层,横向轴线长3m ,根据其形状特点,平面采用“井”型主轴线控制。

利用经纬仪测出建筑物轴线控制桩,经复测合格后(误差不超过2mm),引测至安全、固定位置,做砼护墩加以妥善保护。

建筑物基础轴线采用先龙门桩控制,后经纬仪投测。

先将建筑物四周距基槽边1m 左右,用长钢管打龙门桩,用扣件固定牢固,桩的外侧基本与轴线平行,然后用经纬仪将轴线投测在龙门桩上,用红色三角油漆标绘,再用长钢尺将各轴线定位点测放出来,用红色三角油漆标绘,后重新投测验成,将误差控制在2mm 以内,经复测合格后再依据经纬仪和锤球直接投测到基础上。

其它各层平面轴线控制,主要采用外控法,即用经纬仪竖向投测法中的延长轴线法,基础完成后,用经纬仪投侧或锤球投标到五条轴线的柱外侧,做好红色三角标绘,弹上墨线,施工时以内控制轴成法用吊线坠相结合双向控制,每投测一层,必须进行复测、验线。

(2)高程控制水准点在基础土方开挖时,应在基坑四边设桩刷一条竖向白漆带。

然后根据已知高程控制点,通过三点水准测量进行引测。

对测量成果进行平差后,确定其最终结果,用红色油漆三角标绘,再根据原始± 0.000 标高控制基础的高程。

±0.000 以上标高的控制,则在每层四角的外边柱上标出标高+0.500 的红色标绘。

每各层标高油底层原始+0.500 标高绘由钢尺一次性向上引,不得分层上引,以防止在倒换钢尺时产生误差。

量取时至少要三个基点同时向上引,由下层传引来的高程点必须由水准仪检查闭合后方可使用。

建筑物总高度偏差不超过3H/1000CHK 建筑物总高且不超过± 15mm 。

每层的梁柱、板各标高均以上引的四边柱标高二次测设控制。

4、变形观测以±0.000 以下工程施工完毕后,则在建筑物上设计院设计所规定的部分分别设立永久性沉降观测点和位移观测点,以后每施工二层,则分别观测一次,直到竣工验收完毕后,每一年测设四次,第二年测设二次,每三年后每年测设一次,直到变形稳定为止。

为了保证变形观测成果的精度,除按规定时间一镒不漏的进行观测外,在观测中应采取“一稳定,四固定”的基础原则。

一稳定是指变形观测依据的基准点,工程基点和被观测物上的变形测点,其点位要稳定。

四固定是指所有仪器、设备在固定;观测人员要固定;观测的条件、环境基础相同;观测的路线,镜位,程序和方法要固定。

第二节土方工程1、土方开挖(1)本工程土方采用机械开挖施工方案。

(2)开挖时,每段沟槽处均应设立两个标高控制点,随挖随测试,即时进行人工清基槽,防止超挖,施工垫层。

(3)如开挖遇地下水时,必须及时做好排水工作,将基坑四周挖250mm 宽的排水沟,在靠水塘的位置挖一个集水坑,用潜水泵直接抽至水塘中或水源进行沉淀后可排入至主干道内污水管道内。

(4)土方开挖完后,应及时请有关方面验收检查,为下道工序尽快创造条件。