建筑工程项目概预算与工程量清单课程大作业——某住宅工程量清单同济大学土木工程***888888某住宅工程量清单计算书1.建筑面积S=[8.94×8.54-4.2×1.3]×3+(4.7×1.72+1.33×0.26)×2×0.5+(5.7+0.24)×3.3=240.69(m²)2.平整场地S=8.94×8.54-4.2×1.3+(5.7+0.24)×3.3+1.5×0.24=90.85(m²)3.挖基础土方a.外墙:L=4.5+5.8+2.5+4.5+4.2+2.2+4.8+4.2+1.3=34(m)S=34×1.2=40.8(m²)b.内墙:L=4.5-1.2+4.2-1.2+4.8+1.2=12.3(m)S=12.3×1.2=14.76(m²)c.车库:L=(3.3-0.6+0.4)×2+5.7-0.8=11.1(m)S=11.1×0.8=8.88(m²)d.总挖土:V=(40.8+14.76+8.88)×[-0.3-(-0.97)]=43.17(m³)4.土方回填4.1室内回填土:房屋内主墙间净面积:S=(4.5-0.24)×(5.8-0.24)+(4.2-0.24)×(4.8-0.24)+(2.5-0.24)×(4.5-0.24)+(2.2-0.24)×4.2+1.5×0.24+0.9×0.24×2=60.3948(m²)室内回填土体积:V=60.3948×(0.3-0.07-0.02-0.12)=11.96(m³)4.2基础回填:设计室外地坪以下所埋的基础体积:V=[(0.07+0.15)×1.2+(0.6+1.2)×0.2×0.5+0.12×0.36+0.24×0.13]×(34+12.3)+[(0.07+0.15)×0.8+(0.6+0.8)×0.2×0.5+0.12×0.36+0.24×0.13]×11.1=28.34(m³)基础回填:V=43.17-28.34=14.83(m³)5.砖基础L=4.5+5.8+2.5+4.5+4.2+2.2+4.8+4.2+4.5-0.24+4.2-0.24+4.8+1.3+3.3+3.3+5.7-0.24+1.5=60.58(m)V=60.58×(0.36×0.12+0.37×0.24)=8.00(m³)6.砖墙a.外墙工程量(不扣除梁、门窗、洞):外墙中心线长:L=4.5+8.3+8.7+8.3+4.2=34(m)外墙砌体:V=34×8.85=300.9(m³)b.内墙工程量(不扣除梁、门窗、洞):内主墙净长:L=4.5-0.24+4.2-0.24+4.8=13.02(m)内墙砌体:V=13.02×8.85=115.227(m³)c.车库墙体(不扣除梁、门窗、洞):V=(3.3×2+5.7-0.24+1.5)×3.0=40.77(m³)d.门窗、洞、走道体积(不包括隔墙):V=[(2.4×0.9×3+2.4×0.9×4+0.6×1.5+1.5×1.2×2+1.5×0.9×13+0.25×3.14159×0.7×0.7×3+2.1×2.7+2.1×1.5+0.9×2.2×5+2.4×1.05+2.1×2.4+(1.5-0.12)×2.75+(1.5-0.12)×(3-0.13)+1.5×(3-0.13)]×0.24=18.40(m³)e.圈梁、过梁、雨篷梁体积:圈梁: V=0.18×0.24×[(8.3×2+8.7×2+4.2-0.24+4.8+3.02)×3+3.3×2+5.7-0.24+1.5]=6.52(m³)过梁:V=0.18×0.24×(1.4×33+2+1.7×2+3.2+2+1.3+1.55+2.9)=2.70雨篷梁:V=0.24×4.2×(0.6+0.6+0.45)=1.66(m³)f.隔墙:S=(2.2-0.24+4.2-0.24)×(3-0.13)+(2.5+2.8)×2.25×0.5+1×2.8+[(2.2-0.24)×2+(4.5-0.24)]×(3-0.13)+[(2.2-0.24)×2+(4.5-0.24)]×(2.85-0.1)=71.72(m²)V=71.72×0.12=8.61(m³)g.隔墙门体积:V=0.9×2.2×8×0.12+2×0.8×0.12=2.09(m³)h.砌体总体积:V=300.9+115.227+40.77-18.40-6.52-2.70-1.66+8.61-2.09=434.14(m³)7.混凝土带形基础房屋带形基础:V=[(0.07+0.15)×0.12+(0.6+1.2)×0.2×0.5]×(34+12.3)=20.56(m³)车库带形基础:V=[(0.07+0.15)×0.8+(0.6+0.8)×0.2×0.5]×11.1=3.50(m³)混凝土带形基础:V=20.56+3.50=24.06(m³)8.混凝土梁8.1.基础梁:V=0.06×0.24×60.58=0.87(m³)8.2.过梁:V=0.18×0.24×(1.4×33+2+1.7×2+3.2+2+1.3+1.55+2.9)=2.70(m³)8.3.圈梁:V=0.18×0.24×[(8.3×2+8.7×2+4.2-0.24+4.8+3.02)×3+3.3×2+5.7-0.24+1.5]=6.52(m³)8.4.连系梁:V=(4.7+3.05+0.04+0.26)×2×0.15×0.4=0.97(m³)9.混凝土板9.1.现浇混凝土板:a.100厚现浇板:平屋面:S=(4.2+4.5+1.5)×(7+1.5+1.5)-(4.2×1.5)=95.7(m²)V=95.7×0.1=9.57(m³)二层、三层、阳台中100厚板:V=(2.2-0.12)×3.02×2×0.1+(2.2-0.24)×3.02×2×0.1+[(4.7-0.24)×1.6+0.14×1.33]×0.1×2= 3.90(m³)b.120厚板:S=[(4.5-0.24)×(5.8-0.24)+(4.2-0.24)×(4.8-0.24)+(2.2-0.24)×(3.2+2.48-0.24)+1.24×0.54]×2-(2.2-0.12)×3.02×2-(2.2-0.24)×3.02×2=81.00(m²)V=81.00×0.12=9.72(m³)c.总体积:V=3.90+9.72+9.57=23.19(m³)9.2.预制混凝土板:V=3.3×0.5×11×0.12=2.18(m³)10.混凝土楼梯S=(1.12+2.25-0.12)×2.26-(1×1.26)+(1.12-0.12+1.75+0.15)×2.26=12.64(m²)11.屋面防水S=(4.2+4.5+1.5)×(7+1.5+1.5)-(4.2×1.5)=95.7(m²)12.整体面层(楼地面)12.1.细石混凝土面层:地面(车库):S=(5.7-0.24)×(3.3-0.24)=16.71(m²)楼面:S=81.00-0.88×(2.2-0.24)×2-1.24×(4.7-0.12)×2+(2.2-0.12)×3.02=72.47(m²)总面积:S=16.71+66.19=89.18(m²)12.2.水磨石面层:地面及楼梯间:S=60.3948-(2.2-0.24)×(4.2-0.24-0.9-0.12)=54.63(m²)走道:S=0.88×(2.2-0.24)×2+1.24×(4.7-0.12)×2=14.81(m²)总面积:S=54.63+14.81=69.44(m²)12.3.水泥砂浆面层:地面及楼梯间:S=60.3948(m²)楼面(厨房、厕所加走道):S=(2.2-0.24)×(3.02-0.12)×3+14.81=31.86(m²)总面积:S=60.3948+31.86=92.26(m²)13.踢脚线a.一层:L=(5.8-0.24)×2+(4.5-0.24)×4+(2.5-0.24)×4+(4.2-0.24)×6+(4.8-0.24)×6+(4.8-0.24)×2-0.9×8-1.05-0.9×2-1.5×2=58.83(m)b.二层:L=58.83+(4.5-0.24-0.9)×2+0.15+(2.2-0.24-0.9)×2+1.5×2+(4.2-0.24-0.9)×2=64.7(m)c.三层:L=64.7-0.9=63.8d.车库:L=(5.7-0.24)×2+(3.3-0.24)×2-2.4-1.5=13.14e.S=(63.8+64.7+13.14+58.83)×0.15=30.07(m²)f.扣去厨房厕所及楼梯(楼梯另算):S=30.07-[(4.5-0.24-0.9)×2+(2.5-0.24)+(2.2-0.24-0.9)+(2.2-0.24)+3.02×2]×0.15-[3.02×2+(2.2-0.24)+(2.2-0.24-0.9)]×0.15×3-[(3.02-0.12)×2+(2.5-0.24)]×2×0.15=20.869(m²)g.加上阳台及楼梯(算斜线):S=20.869+[(4.7-0.24)×2+1.6×2+1.33×2-0.9×2]×0.15×2+[2.3×4+2.5-0.24-0.26+1+2]×0.15+2.88×2×0.15=27.75(m²)14.内、外墙面抹灰(镶贴)14.1.内墙抹灰:a.一层:S=58.83×2.88+0.8×0.9×8+0.6×1.05+0.6×0.9×2-0.25×3.14159×0.7×0.7-2×0.9×1.5-2.1×2.7-2.1×1.5=165.00(m²)b.二层:S=64.7×2.88+0.8×0.9×8+0.6×0.9×3-0.25×3.14159×0.7×0.7-5×0.9×1.5-1.2×1.5=184.79(m²)c.三层:S=63.8×2.75+10×0.8×0.9+0.6×0.9×2-6×1.5×0.9-0.25×3.14159×0.7×0.7-1.5×1.2=173.45(m²)d.车库:S=[(5.7-0.24)×2+(3.3-0.24)×2]×2.6-2.1×2.4-0.6×1.5=38.36(m²)e.总面积:S=38.36+172.06+192.55+179.83=523.24(m²)f.减去厕所厨房和楼梯部分:S=523.24-[(3.02-0.12)×4+(2.5-0.24)+(2.2-0.24)×2]×2.88+[(3.02-0.12)×6+(2.5-0.24)+(2.2-0.24)×4]×2.88+[(3.02-0.12)×6+(2.5-0.24)+(2.2-0.24)×4]×2.75=317.21(m²)14.2.外墙斩假石勒:S=[8.54+8.84+4.8+2.2+1.3+3.3+0.24+5.7+4.5+0.24+3.3+1.5-(0.9×2+1.05)-2.4]×0.6=23.59(m²)14.3.外墙面砖a.一层(未扣去门窗、洞):S=(4.5+8.54+8.94+2.2+4.8+1.3)×2.7+4.46×0.65=84.66(m²)b.二层、三层(未扣去门窗、洞):S=(8.94+8.54)×2×5.85=204.52(m²)c.车库(未扣去门窗、洞):S=(5.7+0.24+3.3+0.24+3.3+1.5)×2.7=29.65(m²)d.总面积(扣去门窗、洞):S=84.66+204.52+29.65-1.5×0.9×13-2.4×0.9×7-1.5×1.2×2-0.25×3.14159×0.7×0.7×3-0.6×1.5-2.1×2.7-2.1×2.4-2.4×1.05-2.1×1.5=264.11(m²)15.天棚抹灰S=60.3948×3+2×[(4.7-0.24)×1.6+(0.38-0.24)×1.33]=195.83(m²)。