预留洞封堵施工方案

精心打造目录一、 编制依据········································································2 二、工程概况········································································2 三、施工准备········································································3 四、放线洞、泵管洞封堵操作工艺······················································3 五、工字钢预留洞封堵操作工艺························································5 六、厨卫等处预留洞封堵操作工艺······················································6 七、质量保证措施····································································9 八、安全保证措施及文明施工·························································10未来1精心打造一、编制依据:1、本工程施工合同 2、本工程施工图 3、本工程涉及的国家或行业规范、规程、技术法规、标准、图集,地方标准、图集 4、本工程施工组织设计 5、公司相关管理办法 6、江苏省《住宅工程质量通病控制标准》DGJ32/J16-2014二、工程概况:本工程预留洞口封堵部位为: 1. 在结构施工时,安装专业在楼板、墙板上预留了后期安装时需要穿过楼板的预留洞或预埋了套管:卫生间、管道井、厨房、阳台等。

2. 在结构施工时放线洞(上口 200*200mm,下口 150*150mm)、泵管洞(上口 250*250mm,下口 200*200mm)。

3. 在结构施工时 2#、7#楼的 4 层、10 层、16 层、22 层、28 层及 1#、6#楼的 5 层、11 层、17 层、23 层、29 层的挑架 16#工字钢预留洞(150*250mm)。

预留洞在后期都需要进行封堵处理,为保证后浇洞施工质量,消除建筑水电的渗漏问 题,特制订本方案。

三、施工准备1、材料及要求: 所用材料的品种、规格应符合设计和规范的要求。

材料:标准钢管、顶撑、扣件、15 厚胶合木模板、硬方木、水泥、商品混凝土2、主要机具: 用具:斗车、木(铁)锤、钢錾子、直尺、铁抹子、铁丝、线锤、铁锹等。

3、作业条件: 管道施工已完成及具备洞口封顶条件,经检查验收合格。

为施工操作必须设有防护盖板,确保施工的操作安全。

4、劳动力准备 由于本次封堵涉及洞口分部较广,涉及质量、安全等问题比较多,为了加强全面控制和管理,提早完成任务,进行现场的组织、协调管理工作,并保证施工质量、进度,施 工现场根据施工总进度分段封堵即放线洞、泵管洞→卫生间等→挑架洞。

劳动力安排 20 人以上,积极整合现场资源,合理安排工序,保证日工作效率。

5、技术准备未来2精心打造5.1、熟悉施工图纸; 5.2、对施工班组做好技术交底,明确施工工艺,施工质量要求; 5.3、重点做好洞口封堵灌浆料施工质量控制,确保外墙不漏水。

四、放线洞、泵管洞封堵操作工艺1、工艺流程: 基层处理→植筋→支模→洞口边处理→混凝土封堵→混凝土养护→模板拆除→板底打磨 2、基层处理: 放线洞、泵管洞封堵按一层一次清理,并将洞口部位松散混凝土凿除,用水清洗干净。

3、植筋:洞口四周用Φ6@80 植筋。

4、支模: 支模时用钢管加顶撑,将模板顶牢固,严禁采用铅丝吊模,防止漏水。

底模与楼板缝隙应严密(见下图)。

未来3精心打造5、洞口边处理: 在周边混凝土充分湿润后,用素水泥浆将洞口周边涂抹均匀,其配合比与砼内的砂浆成分相同。

未来4精心打造6、混凝土封堵: 洞口边处理完毕后,浇筑比楼板混凝土标号高一级的细石混凝土,浇筑时按楼层由下往上浇筑。

为防止渗漏发生,采用分层堵洞法,这种方法彻底解决了因堵洞不密实而产生的渗漏问题。

具体做法如下:刷完一道水泥浆后,先用细石混凝土浇筑第一层,高度为洞高的 1/2,用手工插捣密 实。

第二天进行面层混凝土浇筑,混凝土浇筑完成后应压实抹平。

分层浇筑有效地避免因 混凝土收缩产生的通缝,并能使其每层收缩缝相互错开,起到层层设防的作用。