工程设计管理办法文件编号:GCGL第005号目录第一章总则 ···············································································································第二章设计任务书制定及设计成果审核发放 ········································································第三章施工图收发、会审、交底 ·······················································································第四章附则 ···············································································································施工图评审单(GCGL-表19) ····························································································施工图评审意见审批表(GCGL-表20) ················································································第一章总则第1条为加强工程设计的管理工作,使之程序化、规范化,确保工程设计质量,提高产品品质,有效地进行成本控制,结合公司实际情况,制定本办法。
第2条本办法适用于公司工程项目建筑工程设计和各专业设计过程中的方案设计、初步设计、施工图设计阶段的任务书制定、设计成果审核、施工图发放管理。
第3条本办法所称设计包括建筑工程项目中的建筑、结构、水暖、电气各专业设计以及专业设计包括智能化、园林景观、煤气、电话、有线电视、宽带各专业设计。
第4条本办法中所指设计单位是指已经按照《工程建设发包管理办法》中的有关规定取得设计承包的单位。
第5条工程管理部负责设计任务的发包以及对有关设计单位的协调管理。
工程管理部应按照《工程建设发包管理办法》中的有关规定实施设计任务发包,并按设计单位要求向设计单位提供有关设计资料。
工程管理部负责组织对设计单位的设计成果组织审核、验收和设计成果的发放、存档。
第二章设计任务书制定及设计成果审核发放第6条工程管理部按照设计程序和步骤组织方案设计。
1、工程管理部负责按照公司批准的“项目策划书”(或者工程管理部提出的单个项目建设意见),拟订“产品策划书”,按规定流程审批。
2、工程管理部负责按照公司批准的“产品策划书”,并根据政府批准的《选址意见书》和《规划设计条件书》的要求拟订项目“规划及建筑方案设计任务书”,按规定流程审批。
3、工程管理部负责组织设计单位考察项目地址和周边环境,前期开发部负责到当地规划管理部门征求方案设计意见。
4、工程管理部应根据项目实际需要,拟订工程设计考察方案,按规定流程审批。
5、前期开发部负责组织规划管理部门和设计单位相关人员进行设计考察,并编撰设计考察报告,对拟订的方案设计任务书提出修订意见,按规定流程审批。
6、工程管理部应向设计单位提供以下设计资料:1)方案设计任务书;2)政府批准的《选址意见书》和《规划设计条件》;3)宗地地形图和红线图;4)规划部门的指导意见;5)环境评价报告;6)城市给排水、供热、供电、智能、电讯接管位置;7)周边城市道路竖向高程、红线位置及测量成果。
7、工程管理部负责组织项目策划师、产品策划师向规划师、建筑师进行设计任务交底,对提供的设计资料进行详细解答,与设计师进行充分交流沟通,使设计师充分了解项目的内涵和要达到的目标,以使其设计能够最准确地体现出来。
这个过程要反复多次,直至工程设计规划方案达到要求。