太原恒大檀溪郡首期(1地块)冬季五防施工安全应急预案编制人:审核人:审批人:山西省宏图建设集团有限公司二〇一八年目录一、编制理由和依据··········································二、任务与目的··············································三、应急准备················································四、应急响应················································五、报警····················································六、现场医护救援···········································七、应急救援专业队伍成员名单·······························八、项目经理部防火管理条例··································九、防煤气中毒安全措施及安全预案····························十、触电事故应急处置········································十一、冬季施工防滑防冻措施··································十二、机械事故应急预案······································十三、预案管理·············································十四、预案修订与完善········································十五、应急物资及装备········································已经进入冬季,我项目部紧紧围绕冬季安全生产,采取了多项措施抓好冬季防火、防冻、防滑、防止煤气中毒、防意外伤害等“五防”工作,确保了冬季安全生产的万无一失。
项目部在依照国家及地方相关的法律法规并结合本标段实际情况制定了“冬季施工五防工作应急预案”,明确了“五防”工作重点和“五防”责任人,加大了安全检查和宣传教育力度。
在防火上,认真检查了施工现场的电线、电缆、用电设施、生活用电以及施工机械、车辆电器线路的安全性能情况,保证用电线路能在正常负荷范围内运行。
在防冻方面,对施工机械、车辆添加优质防冻液,保证冬季安全运行、安全行车。
定期对施工机械、车辆进行检查、维护保养,使施工机械、车辆在冬季能正常运行。
对施工现场的风、水管采取保温防冻措施,防止冻结、冻裂。
在防滑方面,当遇到雪天作业时,要求对作业面的积雪进行清扫完成后方可作业。
在防煤气中毒方面,严格禁止冬季煤火取暖,以防止煤气中毒。
此外,桥梁施工单位还加强了冬季高空作业人员的职业安全防护能力,避免大风天气进行高空作业,严格按照施工规范及设计文件组织施工。
进入冬季,气候干燥天气寒冷,是火灾、煤气中毒等安全问题的高发季节,为了最大限度降低各类事故的发生率和受害率,力求早发现、早出动、早处理,根据《中华人民共和国安全生产法》和其他有关规定,结合本标段实际情况,制定本预案。