挖土体积=挖基坑体积+挖沟槽体积=390.456+8.5307=398.9867
室外地坪以下的基础工程量的体积=基坑垫层体积+独立基础体积+室外地坪以下柱和梁体积(阳台暂不计)
室外地坪以下柱体积=0.5×0.5×28(1.3-0.45)+0.5×0.6×4(1.2-0.45)=6.85
室外地坪以下梁体积=0.3×(0.65-0.45)×(112.4+157.479)=16.1927
KL7梁断面300×500,梁长=16.2-0.5×3=14.7
体积=梁断面×梁长×2=4.41
合计:2.49+8.28+5.145+4.41=20.325
KL4梁断面300×600,梁长=7.2-0.5=6.7同定额量
体积=梁断面×梁长×1=1.206
KL8梁断面300×600,梁长=(7.2-0.5)×2+(6.9-0.5)×2=26.2
走廊:15.3×1.6×(0.45-0.3) ×2=7.344
卫生间:3.2×6.95×(0.45-0.22) ×2=10.2304
办公室1:(2~3/A~B)5.8×7.25×0.22=9.251
(2~3/C~D) 5.8×6.95×0.22=8.8682
(3~4/A~B,1/4圆上面积+1/4圆左面积+1/4圆面积) (5.8×4.75+2.5×3.4+3.14×2.5×2.5/4)×0.22=9.0104
③④弧长=(6.0-2.5-0.25+2×3.14×2.35/4-0.25)×2=13.38
梁长合计:58.5+29.2+24.4+102.9+24.6+16.6+13.38=269.885m
体积=0.3×0.55×梁长=0.3×0.55×269.885=44.53
44.53
1
回填土方
m3
1.基础回填=挖土体积-室外地坪以下的基础工程量的体积
41.38
KL2梁断面300×500,梁长=9.3-0.5×2=8.3同定额量
体积=0.3×0.5×8.3×2=2.49
KL5梁断面300×500,梁长=15.3-0.5×3=13.8
体积=梁断面×梁长×4=8.28
KL6梁断面300×500,梁长=37.8-0.5×7=34.3
体积=梁断面×梁长=5.145
JC-2’:4.6×2.5×0.3+1/6×0.2×[4.6×2.5+(4.6+2.7) ×(2.5+0.6)+2.7×0.6] ×2=9.2833
合计:6.2827+7.632+22.896+40.302+7.92+7.92+9.2833=102.236
102.24
1
基础梁
C30
m3
体积=梁断面×梁长同定额
合计:15.7+23.5+23.4+46.8+9.36+9.36=128.12
129.14
梯柱TZ1首层TZ1:0.3×0.2×(1.95+0.1)×3=0.369同定额量
二、三层TZ1:0.3×0.2×1.8×3×2=0.648
合计:0.369+0.648=1.017
总计:128.12+1.017=129.137
体积=梁断面×梁长=4.716
KL9梁断面300×600,梁长=16.2-0.25-0.5×2-0.35=14.6
体积=梁断面×梁长×2=5.256
KL10梁断面300×600,梁长=13.7-0.5×3=12.2
体积=梁断面×梁长×2=
合计:1.206+4.716+5.256+4.392=15.57
1
构造柱GZ C25
m3
以C2424两侧为例同定额量
首层={[0.25×0.25×(3.9-0.5)+0.05×0.25×3.4+0.05×0.25×(3.4-2.4)]-0.05×0.18×0.25}×4=1.052
二层={[0.25×0.25×(3.6-0.5)+0.05×0.25×3.1+0.05×0.25×(3.1-2.4)-0.05×0.18×0.25]}×4=0.9472
总计:28.072+118.784+144.768+61.248+3Hale Waihona Puke .584=390.456挖沟槽
m3
沟槽净长×地梁宽×沟槽深
1
DL-1
梁宽300
挖深0.2m
沟槽净长:(16.2-7)×2+(16.2-8.4) ×2+(16.2-8.5) ×2+(4.7+2.1+6.9-8.4) ×2+(37.8-21.9) ×2+(9.3-5.9) ×2+(3.5-1.6) ×2+(2×3.14×2.35/4-1.6) ×2+(7.2-0.3)+(6+7.2+6-6.9)=142.178
地梁宽:0.3
沟槽深=0.65-0.45=0.2
8.53
体积=142.178×0.3×0.2=8.5307
2
砖带型基础
宽700
挖深0.59m
m3
长度=(1.66-0.25)×2+(1.88+1.66)×2=9.9
垫层宽=0.7
沟槽深=1.04-0.45=0.59
体积=长×宽×深=9.9*0.7*0.59=4.0887
m3
KL1梁断面250×500,梁长=6-2.5+2×3.14×(2.5-0.125)/4-0.5=6.7291同定额量
体积=梁断面×梁长×2=1.6823
KL3梁断面250×500,梁长=(6-0.35-0.15)×2+(7.2-0.5)=17.7
体积=0.25×0.5×17.7=2.2125
合计:1.6823+2.2125=3.8948
断面面积=【0.04725+0.24×(1.04-0.1-0.1-0.24)】=0.2152
体积=断面面积×长度=0.2152×9.9=2.1304
2.13
首层砌块墙
m3
外墙长度=(4.7+0.6+2.1+6.9-0.5-0.5-0.25)×2+(37.8-0.5×7-7.2+0.5)+(6+1.4-0.5-0.25)×2+(7.2-0.5)=73.7
回填土体积=398.9867-26.928-102.236-6.85-16.1927=246.78
254.25
2.室内回填(房心回填) =主墙间净面积×回填厚度同定额
首层大堂:7×(3.65+2.1+4.7+0.25)×(0.45-0.3)=11.235
楼梯间:7×(6.9-3.65+0.25)×(0.45-0.23)=5.39
JC-1:2×2×0.3+1/6×0.2×[2×2+(2+0.6) ×(2+0.6)+0.6×0.6] ×4=6.2827
JC-2:3×3×0.3+1/6×0.3×[3×3+(3+0.6) ×(3+0.6)+0.6×0.6] ×2=7.632
JC-3:3×3×0.3+1/6×0.3×[3×3+(3+0.6) ×(3+0.6)+0.6×0.6] ×6=22.896
办公室2:(1~2/A~B+1轴左+1轴右部分面积)[3.2×7.3+(1.78-0.1)×(3.78-0.2)+(2-0.1) ×(1.78-0.15)] ×0.23
=32.4714×0.23=7.4684
合计:246.78+7.4684=254.2484
砌筑工程
1
砖基础
m3
长度=(1.66-0.25)×2+(1.88+1.66)×2=9.9
内墙厚度=0.20
1
250厚墙
m3
体积=长度×高度×厚度-门窗洞口面积×墙厚-过梁-圈梁-构造柱-飘窗根部构件体积
2
200厚
墙高3.3
m3
体积=长度×高度×厚度-门窗洞口面积×墙厚-过梁-梯柱体积-梯梁体积
200厚
墙高3.4
m3
3
240厚女儿墙,高0.84
m3
体积=长度×高度×厚度-构造柱GZ1、GZ2体积
梁断面=0.3×0.55
梁长:垂直方向
①②⑦⑧轴=(16.2-1.5)×4=58.8,③⑥轴=(16.2-1.6)×2=29.2
④⑤轴=(13.7-1.5)×2=24.4
水平方向
B、C、D轴=(37.8-3.5)×3=102.9
1/A轴+④⑤=(19.2-1.5)+7.2-0.3=24.6
A轴、①③段+⑥⑧段=(9.3-1)×2=16.6
KZ2:0.5×0.5×[(1.2+14.4)×2+(1.3+14.4) ×4]=23.5
KZ3:0.5×0.5×(1.2+14.4)×6=23.4
KZ4:0.5×0.5×(1.2+14.4)×12=46.8
KZ5:0.6×0.5×(1.2+14.4)×2=9.36
KZ6:0.5×0.6×(1.2+14.4)×2=9.36
4.09
1
独立基础砼垫层
C15预拌
m3
垫层投影面积×垫层厚度×垫层数量同定额