TECHNICAL ANNEX

FOR

EPC CONTRACT

OF

TISCO SECOND STAGE EXPANSION PROJECT VIETNAM TISCO二期扩建工程项目总承包(EPC)合同

技术附件

TECHNICAL ANNEX (VIII)

(GENERAL LAYOUT AND TRANSPORTATION, ROADS, RAILWAYS, ALL KINDS OF PIPING NETWORK FOR TISCO’S SECOND STAGE REVANPING

AND EXPANSION PROJECT)

TISCO二期扩建工程之总图运输,公路,铁路,各种管网

2007.7

CONTENTS INDEX

附件目录

1.GENERAL DISCRIPTION OF TISCO’S STAGE II EXPANSION

PROJECT( EPC)

TISCO二期扩建工程概述

2.WORKING SCOPE OF CONTRACTOR

承包商工作范围

3.ADOPTED STANDARDS AND CODES FOR THE PROJECT

项目规范和标准

4.DESCRIPTION OF GENERAL LAYOUT, TRANSPORTATION, ROADWAY,

RAILWAY AND PIPELINE WORKS OF THE WHOLE PLAN (STAGE II)全厂TISCO二期扩建工程之总图运输,公路,铁路,各种管网的

概述

5. EQUIPMENT LIST AND GENERAL LAYOUT ARRANGEMENT

设备清单与布置图

6. SOLUTIONS FOR IMPLEMENTATION ARRANGEMENT

进度打算

1.GENERAL DISCRIPTION OF TISCO’S STAGE II

EXPANSION PROJECT (EPC)

TISCO二期扩建工程概述

2.According to the requirements of sold bidding

document 01#EPC, dated on March. 10, 2007, for the

second stage revamping and expansion project of

TISCO, the long process of steel making production

line with capacity of 500,000t/a casting billet

will be newly built up in the main plant areas of

LUU XA.

3.依照在2007年3月10日卖出的01#EPC—TISO二期扩

建项目投标文件的要求,在LUU XA.主厂区新建

500.000t/a连铸坯生产能力的钢铁冶炼长流程工程。

According to the requirements of bidding document,

Fe metal balance for producing 543,200 t/a hot

metal is shown as following calculation block

diagram:

依照投标文件要求,年产543,200 t铁水中金属铁的比

例如计算框图

1.1MAIN TECHNICAL PROCESS FLOW CHART

要紧工艺流程

LUU XA main plant will adopt a long process production line, namely coke oven, sintering machine, blast furnace, converter, and continuous casting production line.

LUU XA主厂区采纳长流程炼焦、烧结、高炉、转炉连铸生产工艺

01# EPC package mainly includes raw material yard project, coke making project (coke oven), sintering project, iron making project, steel making project, and oxygen generating project, whole plant utilities (water, electricity and natural gas) at the second stage and general layout and transportation.

EPC工程包括的主车间:原料场;炼焦(焦炉)工程;

烧结工程;炼铁工程;炼钢工程;制氧工程;二期全厂

公辅设施(水、电、燃气);总图布置及运输。

1.2CONTENTS OF CONTRACTING

1.3合同内容

The Employer uses the EPC bidding method. The

bidding scope includes main plant area geological

exploration for the second stage project,

engineering design, equipment supply, staff

training, project construction, equipment

installation, test-run, trial production, start up

of production, acceptance test and hand over.

雇主采纳EPC方式招标,其内容包括:主厂区二期的地