当前位置:文档之家› 雨季、冬季、风季施工方案(1)

雨季、冬季、风季施工方案(1)

贵州粤电石阡县大顶山风电场工程季节性施工方案山东电力建设第二工程公司2014年12月30日目录1、编制依据------------------------------------------------------------------------------------------------------------------------------------------------------ 01.1、施工图纸---------------------------------------------------------------------------------------------------------------------------------------------- 01.2、国家现行规范、规程 ----------------------------------------------------------------------------------------------------------------------------- 02、工程概况------------------------------------------------------------------------------------------------------------------------------------------------------- 02.3、季节施工期限及项目 ----------------------------------------------------------------------------------------------------------------------------- 13、季节性施工组织机构 -------------------------------------------------------------------------------------------------------------------------------------- 14、雨季施工措施 ---------------------------------------------------------------------------------------------------------------------------------------------- 24.1、雨季施工管理目标--------------------------------------------------------------------------------------------------------------------------------- 24.2、雨季施工准备 --------------------------------------------------------------------------------------------------------------------------------------- 24.3、审图 ---------------------------------------------------------------------------------------------------------------------------------------------------- 24.4、主要材料、机具计划 ----------------------------------------------------------------------------------------------------------------------------- 24.5、主要施工技术措施--------------------------------------------------------------------------------------------------------------------------------- 24.6.主要管理措施------------------------------------------------------------------------------------------------------------------------------------------ 45、风季施工措施 ------------------------------------------------------------------------------------------------------------------------------------------------ 55.1、施工部署---------------------------------------------------------------------------------------------------------------------------------------------- 55.2、一般措施---------------------------------------------------------------------------------------------------------------------------------------------- 55.3.专项施工措施------------------------------------------------------------------------------------------------------------------------------------------ 66、冬季施工措施 ------------------------------------------------------------------------------------------------------------------------------------------------ 76.1、气象资料收集及记录工作----------------------------------------------------------------------------------------------------------------------- 76.2、冬季施工准备工作--------------------------------------------------------------------------------------------------------------------------------- 76.3、冬季施工专项措施--------------------------------------------------------------------------------------------------------------------------------- 96.4、冬施安全注意事项------------------------------------------------------------------------------------------------------------------------------- 16 1、编制依据1.1、施工图纸1.1.1、《贵州粤电石阡县大顶山风电场工程设计文件》。

1.1.2、《贵州粤电石阡县大顶山风电场工程岩土工程勘察报告》。

1.2、国家现行规范、规程1.2.1、混凝土结构工程施工质量验收规范(GB50204-2002)1.2.2、建筑地基基础工程施工质量验收规范(GB50202-2002)1.2.3、建筑工程冬期施工规程(JGJ 104-97)2、工程概况石阡县大顶山风电场位于贵州省铜仁市石阡县和江口县境内,与石阡县城区公路里程约52km,与江口县城区公路里程约70km,地理坐标介于东经108°31′~108°35′,北纬27°31′~27°35′之间,场区地面高程1300m~1520m,场址范围面积为15.4km2。

大顶山风电场场址北部有省道S305、S303,场址距石阡县道路运输距离约52km,与江口县城区公路里程约70km,交通较为便利。

本工程拟安装24 台单机容量为2.0MW 的风力发电机组,相应装机规模为48MW,预计年上网电量为9603万kW·h。

2.3、季节施工期限及项目根据历年来石阡县天气情况,每年3月15日至7月30日为石阡县降雨量高峰期,每年10月20日至次年4月10日为冬季施工期,根据本工程的总控进度计划安排,冬、雨季施工期间主要施工部位为:2.3.1、雨季施工根据石阡县气象资料,降水集中在3、4、5、6四个月,故雨季施工为2015年3月1日至2015年6月1日基本结束,在设定的雨季施工期外,如遇集中降雨,同样适用于本方案。

雨季施工主要作业内容:风机基础工程、风机道路工程、风机吊装工程、升压站:主体结构施工、砌筑工程、抹灰工程、机电安装工程、门窗工程、室内外装修工程。

2.3.2、冬季施工石阡县冬期施工从10月25日起至第二年的3月1日(或至连续5天平均气温高于5℃为止),当室外温度低于-15℃时停止施工,进入冬歇期。

当室外日平均气温连续5天高于5℃解除冬期施工。

具体冬施期限根椐现场大气测温值确定。

2014年10月20日——2015年3月10日,主要作业内容为:风机道路工程。

2.3.3、风季施工根据本工程的工程特点和进度计划,风季主要施工部位如下:2014年冬季风机道路工程2015年春季风机道路工程、风机基础工程、升压站主工程、升压站电气安装工程。

2015年秋季内外装修工程、机电安装工程。

3、季节性施工组织机构为保证工程安全有序的进行,项目经理部成立季节性施工领导小组,具体落实雨季施工前的各项准备工作及解决雨季施工中的生产问题。

组长:赵伟(季节性施工期间现场总指挥)副组长:唐湘(季节性施工各项工作的具体落实,现场作业人员调配、冬施物资的管理)副组长:郑福林(季节性施工技术的指导、监督、落实)组员:杨振(季节性施工方案的实施、监管)刘兴旺(季节性施工分项工程的质量监督控制)杨文清(季节性施工现场安全监督、检查)李飞(季节性施工物资调配、供应)4、雨季施工措施4.1、雨季施工管理目标4.3.1、雨季施工主要以预防为主,采取防雨及加强排水措施,确保雨季生产的正常进行,尽量减少因季节性气候对工程施工的影响。