SALES CONFIRMATION Contract No.: DF059 Date: DEC 5, 2009
Buyer: CHUNG CHEMICALS AND BHD
Address: 641-2, 4TH MILES, JALAN IPOH, 51200 KUALA LUMPUR, MALAYSIA.
Tel: ××××Fax: ××××
The undersigned Sellers and Buyers have agreed to close the following
HUNDRED EIGHTY EIGHT ONLY.
TIME OF SHIPMENT: LATEST MARCH 5, 2010
QUANTITY MORE OR LESS:5%
LOADING PORT & DESTINATION:FROM SHANGHAI TO PORT KLANG PARTIAL SHIPMENTS:NOT ALLOWED
TRANSHIPMENT: NOT ALLOWED
PACKING: PACKED IN IRON DRUMS OF 165KGS NET EACH.
INSURANCE: TO BE COVERED 110% FOR THE INVOICE V ALUE AGAINST WAR RISK AND ALL RISKS.
MARKS & NOS: AT SELLER'S OPTION.
PAYMENT: BY IRREVOCABLE L/C AT SIGHT TO REACH THE SELLER
45 DAYS BEFORE SHIPMENT.
THE BUYER THE SELLER
CHUNG CHEMICALS AND BHD (AUTHORIZED SIGNATURE) JIANGSU DONGFANG PETROCHEMICALS WORKS
(AUTHORIZED SIGNA TURE)
审查以上合同,回答以下问题:
一.翻译
1.TIME OF SHIPMENT: LATEST MARCH 5, 2010
LOADING PORT & DESTINATION:FROM SHANGHAI TO PORT KLANG PARTIAL SHIPMENTS:NOT ALLOWED TRANSHIPMENT: NOT ALLOWED
2.Name of commodity and specification:GRADE A WHITE OIL
1× 20' CONTAINER
Quantity:13.2 M /T
Unit Price :USD590.00 PER M/T CIF PORT KLANG
PACKING: PACKED IN IRON DRUMS OF 165KGS NET EACH.
二.回答问题:
1.本合同项下订单的付款方式是什么?
2.合同规定“PAYMENT: BY IRREVOCABLE L/C AT SIGHT TO REACH THE SELLER 45 DAYS BEFORE SHIPMENT”对卖方有利吗?为什么?3.本合同项下,最多可以装多少M/T?最少可以装多少M/T?
4.按照本合同规定,由哪一方投保?为什么?
5.按照本合同约定,应投保什么险别?
6.假如出险,被保险人可获的保险金额最高为多少?请写出计算过程。
二.
SALES CONTRACT
NO. MM06125 DATE: MAR. 16, 2007
THE SELLER: HANGZHOU MEIMEI CO., LTD.
NO. 1 YANAN ROAD, HANGZHOU, P.R.CHINA
THE BUYER: ABC CO., LTD.
5 MOON ROAD, HAMBURG, GERMANY
This Contract is made by and between the Buyer and Seller, whereby the Buyer agrees to buy and the Seller agrees to sell the under-mentioned commodity
MORE OR LESS CLAUSE: With 3% more or less in quantity and amount is allowed.
PACKING: 20 pieces packed in one polybag, 10 polybags in one standard export carton.
TIME OF SHIPMENT : Not later than May 15,2007.
PORT OF LOADING AND DESTINATION: Loading port: Hangzhou,China Destination port: Hamburg, Germany.
Transshipment is allowed and partial shipment is not allowed . INSURANCE: 110% of the contract value covered all risks and war risks carried by the seller.
TERMS OF PAYMENT: Irrevocable L/C at sight. If the L/C was late, the
exporter would not take the responsibility of late
shipment and reserve the right of canceling the
contract and asking for compensation from the
buyer.
FORCE MAJEURE:(略)
ARBITRATION:(略)
This contract is made in two original copies and becomes valid after both