摘 要
本设计为工程预算及施工组织设计。选取的题目是新南通生活配套区8#宿舍楼工程造
价与施工组织设计。本工程负一层为半地下车库,地上五层,外加一阁楼层,建筑高度
18.14m,建筑面积2893.55m²,结构形式为砖混结构。
首先是工程造价。通过一点智慧软件计算工程量,综合分析现行建筑市场的人工、材
料、机械等市场价格,编制设计任务书规定范围的工程量定额报价和工程量清单报价。
其次是施工组织设计。根据工程特点划分施工段,确定合理的施工顺序,选择主要分
部分项工程施工方法和主要施工机械,根据工期要求编制合理施工进度计划表,并绘制施
工平面图,以及采取有效的质量、安全等保证措施,例如安全文明施工措施、季节性施工
措施等。本工程包括工程进度、质量、造价三大控制和项目管理机构设计。根据工期要求,
在工程进度调整条件下,绘制调整后进度计划表.另外根据工程特点,确定本工程的质量、
进度、造价等控制要点,进行项目管理机构设计。此外还完成了6张AutoCAD 绘图和外文
翻译。单项作业为个人小结。
关键词:工程量计算,工程造价,施工方案
南通大学毕业设计(论文)
II
Abstract
This design is the budget and construction organization design of the engineering.The
graduation design subject is New nan tong life supporting area 8# dormitory project cost and the
construction organization design.The -1 layer of the project is a underground garage,there are 5
layers overground and a attic, the building is 18.14 meters tall and it’s construction area is
2893.55 square meters, the structure form is brick and concrete structure. the graduation design
consists of three parts which are construction cost ,the construction organization design,and
project management .
Firstly, it is construction cost .The cost of construction project is calculated by Fly. Analysis
the current price of labor, materials, machinery in the construction market and work out the
Fixed price and the detailed list of engineering quantity price.choose construction measures of
main component project and major machine,
Secondly, it is construction organization design. Devide the construction period according
to the features of the project, make sure a reasonable construction sequence, Prepare the
reasonable construction progress schedule on the basis of construction time limit, draw the
construction plan chart and make some measures to protect the quality and safety of the project
like safety civilized construction measures and seasonal construction measures.The project
includes progress,quality and cost control, and project management institutions desigh. Draw
adjusted progress schedule in the progress of the projects under the condition of adjustment,
Draw the construction plan chart. Make sure the project quality, progress, cost and control
points and desigh project management mechanism. In addition,I complete six AutoCAD
paintings, and the personal summary.
Key words: Quantity calculation , Construction cost , Construction method