轻型井点深井降水方案

启东市安置房城东村高层住宅小区轻型井点、深井降水施工方案江苏南通二建集团有限公司2012年4月25日目录一、工程概况···································································3二、编制依据····································································3三、降水方案选择及排水方案···············································41.轻型井点····································································42.深井降水····································································63.排水方案····································································9四、井点、深井降水施工机构及管理人员···························9五、降水时对周边边坡的影响和监测方法··························9六、质量保证措施·······························································10七、安全施工措施················································11八、危险点分析································································13九、安全生产及文明施工措施··············································14十、环保措施································································15 附:现场排水布置图城东村安置房高层小区B标段井点、深井降水方案一、工程概况工程名称:城东村安置房小区B标段工程地址:城东村安置房小区A、B标段位于南苑路南侧,惠阳路东侧,纬一路北侧,秀水路西侧。

建筑面积约292000平方米。

A、B标段中间由原有河道分隔而成。

B标段在A标段南侧(纬一路边侧)。

建设单位:启东市新城建设发展有限公司围护设计单位:启东市建筑设计院有限公司勘察单位:江苏省地质勘察院监理单位:南通瑞达监理有限公司施工单位:江苏南通二建集团有限公司建筑物简况:B标段主要由11幢高层单体和一个地下车库及一些配套啇住辅助用房等,建筑面积约153000平方米。

本工程基坑周长约1300m,基坑形状不规则。

工程地质情况:根据地质报告基坑土体为由1~4层土层构成,第1层素填土,第2层为粉质粘土夹粉土第3层为粉土夹粉质粘土,第4层为粉土夹粉砂。

二、编制依据(1)施工蓝图(2) 《启东市安置房城东村高层小区基坑支护工程施工图》;(3)《启东市安置房城东村高层住宅小区工程勘察报告》(4) 《建筑工程施工质量验收统一标准》(GB50300-2001);(5) 《施工现场临时用电安全技术规范》(JGJ46-2005);(6) 我公司对施工现场进行踏勘了解的有关情况;(7) 江苏省及我公司有关安全、文明施工的文件规定。

三、降水方案选择及排水方案根据启东市建筑设计院有限公司设计的《启东市安置房城东村高层小区基坑支护工程施工图》;基坑降水采用放坡段坑周侧设置一列轻型井点,坑内降水主要采用深井降水。

局部有降水困难的地方在施工过程中考虑增设井点。

1、轻型井点○1轻型井点工作原理:井点降水是利用真空吸力,把地下水位降低,轻型井点主要部件是喷射点内管底端的排水装置,经过总管与主管之间和环形空间直达底端,在喷咀处由于水面的缩小,使工程水流具有极度高的流速,在喷咀附近造成负压,因而将地下水经滤管吸入,吸入的地下水在泵体内混合,然后再把水排出,周而复始,循环工作。

○2施工工艺:井点降水采用水枪冲孔工艺为:定位→开沟→放支管→填砂→安装总管及设备→调试抽水→正式抽水→拆除1、定位根据现场情况和设计图,确定井点布置方位为放坡段周侧外2.5米位置基坑周边一圈。

2、开沟、坑:在轻型井点外侧适宜位置开沟、坑,为排放冲孔用循环水(若表面是杂填土,必须清除至原土)。

3、冲孔采用3BL-9导杆式水冲松成孔,孔径约0.25-0.30m,孔深超过支管(连滤头)长度0.5m。

4、放支管:成孔后迅速放支管,放入后以管口出水为合格。

本工程井点管采用直径48mm的钢管,长度为4.8m,管下端配有与井点管同径的滤管和管尖。

滤管长度为1.2m,滤管壁上钻有呈梅花状的直径为φ12的滤孔。

滤孔面积一般为滤管表面积的15%-20%,滤管壁处包两层滤网内层采用网眼为30-50孔/cm2的尼龙丝布细滤网,外层采用网眼为3-10孔/cm2的尼龙丝布粗滤网,井点管的上端用弯管与总管相连。

5、填砂:安设支管后及时填砂,以粒径为1.2mm至1.5mm粗砂为宜,每孔充填砂约350Kg。

6、安装总管及设备:A、支管和总管用弹簧橡胶软管连接,两端用12#铁丝扎紧后,再用保鲜膜包4-5层,以防漏气。

B、总管和机组连接,机组安设位置以放在总管中部为宜,若考虑排水位置或场地具体情况,亦可放在端处,具体以本现场实际情况定。

7、调试抽水8、正式抽水9、拆除:降水达到要求后,即可进行土方开挖,为降低费用,可采取进场挖机勾住井点管套,直接拔取。

○3施工设计及机具的选择配置(一)施工设计1、基坑开挖深度:2.2m~4.65m(自然地面下)2、支管抽水影响半径:6m3、支管间距:0.9m抽水时间:120天(基坑开挖前15天到±0.00回填土结束并满足建筑物抗浮要求为止)。

(二)机具的选择配置沿基坑周侧设置轻型井点周长1290米,按45米设置一套共需设置29套。

降水设备采用JSJ-690真空泵机,离心泵功率7.5kw,最大抽水量为60m3/h,最大抽吸深度为9.6m,最大提升高度为8m,真空压力必须达到6-8Kg,3BL-9导杆水冲枪四套,井点总管直径为Φ100每节6m,井点管直径为Φ48每根4.8米(插深4.5米)。

○4、施工方案本工程基坑开挖深度为自然地面下2.2m~ 4.65m,抽水设备负荷45米一套,井点支管间距0.9米,支管长度为4.8米(含0.8米滤头),井点降水设备及排水布置详见附图,各套井点管抽出的水均由软管接至邻近沉淀池排出。

本段井点设备及管线安装时间约为四天,土方开挖前预抽水时间约为15天。

2.深井降水○1深井降水方案:基坑采用¢400管井降水,共设249口,其中主楼部份井深9.0米,共94口,地下汽车库部分井深13.0米,共155口。

管井为无砂混凝土管。

深井降水打井及安装时间10天。

降水时间考试为120天。

○2、工艺流程准备工作钻机进场定位安装开孔下护口管钻进终孔后冲孔换浆下井管稀释泥浆填砂止水封孔洗井下泵试抽合理安排排水管路及电缆电路试验正式抽水记录。

○3设备选型本工程降水井孔径最大为φ800mm,根据本公司多年的施工经验,本工程钻井设备选用GPS—10型钻机,成孔采用正循环自然泥浆造浆,泥浆护壁回转达钻进成孔,钻头选用带保径圈的三翼钻头,钻头直径按设计及规范要求。

根据施工经验,使用这些钻头施工稳定性好,能确保成孔质量,能胡效控制成孔中的缩径现象,为确保工程质量奠定基础。

○4、施工技术要求(1)准备工作支撑梁开始后,即开始施工部署,首先组建项目经理部,落实材料和人员,合理安排人财物,与甲方及工地上各相关单位保持密切协作。

(2)材料到位专人负责过料,工程师核定,确保井壁管、过滤管、填料、粘土等到材料的质量。

材料不到位,质量不符合要求不能开钻。

(3)进出场院、定位、埋设护孔管由甲方提供“三通一平”,钻机进场。

钻井井位确定后应由总包方(土建方)认可(井位需微调距梁、柱近距不得小于1.5米),基础牢固,应放在硬粘土或碎石道渣上。

钻机安放稳固、水平、护孔管中心、磨盘中心、大钩应成一垂直线。

埋设护孔管要求垂直,并打入原状土中10—20cm,外围用粘土填实夯实,井管、砂料到位后才能开钻,钻孔孔斜不超过1%,要求整个钻孔孔壁圆整光滑,钻进时不允许采用有弯曲的钻杆。

(4)钻进清孔钻进中保持泥浆比重在1.1—1.15,尽量采用地层自然造浆,整个钻进过程中要求大钩吊紧后徐徐给进(始终处于减压钻进),避免钻具产生一次弯曲。

特别是开孔时不能让机上钻杆和水接头产生大幅摆动。

每钻进一根钻杆应重复扫孔一次,并清理孔内泥块后再接新钻杆,终孔后应彻底清孔,直到返回泥浆内不含泥块,返出的泥浆含砂量<12%后提钻。

(5)下井管按设计井深事先将井管排列、组合,下管时所有深井的底部按标高严格控制,并且保持井口标高一致。

井管应平稳入孔,每节井管的两端口要找平,确保连接垂直,完整无隙,外包竹片双层滤布铁丝固定捆绑,以免脱落。

为了保证井管不靠在井壁上和保证填料厚度,在滤水管上下部各加一组扶正器,保证环状填料间隙厚度不大于180mm,过滤器应刷洗干净,过滤器缝隙均匀,外包一层40目滤网。

下管要准备到位。

自然落下,稍转动落到位,不可强力压下,以免损坏过滤结构。

井管到位后下钻杆泥浆稀释到1.05左右,在稀释泥浆时井管管口应密封,使泥浆从过滤器经井管与孔壁的环状间返回地面,稀释泥浆应逐步缓慢进行。

井管上口高度高出地面0.5米。

(6)填料稀释泥浆比重在1.05~1.08后关小泵量,将填料(疏干井的填料为建筑砂和瓜子片的混合物,承压井的填料为砾砂)徐徐填入,并随填随测填砂顶面的高度,不得超高。

设计钻孔直径800mm,井管直径、填料厚度、填砂高度严格按设计图纸进行。

(7)止水填料层上部2m左右用粘土填实。

(8)联合洗井用空压机洗井并清除井底存砂。

(9)下泵抽水井施工结束后,用泵进行抽水并对井验收评定。

3排水方案○1在基坑开挖前在场地临时主干道四周边侧辅设一圈DN500玻纹管每隔50米砌一座沉淀池,东、西、侧排水均向北侧排放由北侧沉淀池连接的DN500玻纹管排到北侧河中。

南侧排水通过围墙外预埋的东、西方向的DN600玻纹管(每隔25m设内径1000×1000的检查井)由东向西排到西侧大河中。

○2基坑边井点降水、深井降水排水管就近接入DN500玻纹管中。

四、井点、深井降水施工机构及管理人员五、降水时对周边边坡的影响和监测方法○1、降水对周边建筑物影响的分析:由于本工程设在市郊安置小区,距周边建筑物、道路过远,大面积开挖基坑,基本上对周边建筑物和周边道路不会产生影响,本工程基坑降水采用井点和深井降水基坑开挖后,为确保施工安全,在施工期间,应对外围基坑边坡采取如下监测方法:○2、监测方法:施工期间主要对场外水位变化、周边的外围基坑边坡变形进行观测,井点降水进行前观测的数据作为起始数据,随着基坑水位下降,以起始数据为基础,进行水位、周边的建筑物垂直度和沉降观测,做好记录。