甪直至板桥110KV双回线路工程高压电缆安装作业指导书编码:SDXL-ZW-13SDXL-ZW-13 高压电缆安装作业指导书目次1 工程概况及适用范围 (14)12 编写依据····································································································································· (141)3 作业流程····································································································································· (141)4 安全风险辨析与预控 (14)25 作业准备····································································································································· (142)6 作业方法····································································································································· (143)7 质量控制措施及检验标准 (146)2 / 131 工程概况及适用范围1. 1适用范围本作业指导书适用于110~500kV 电压等级交联电缆预制式中间接头、终端头安装。
1.2 工程简述本工程电缆起于220KV甪直变电所西侧110KV间隔的南起3#、4#间隔,至于110KV板桥变(现更名为凌港变)西侧南起备用5#、6#间隔,电缆路径总长度约2560m,电缆型号选用YJLW0364/110KV-1*800mm ²电力电缆2编写依据表2-1 编写依据序号引用资料名称1GB 50168—2006《电气装置安装工程电缆线路施工及验收规范》2DL/T 5161.1~5161.17—2002《电气装置安装工程质量检验及评定规程第5部分电缆线路施工质量检验》3DL4Q/CSG 10002—2004《架空线路及电缆安健环设施标准》5Q/CSG 10010—2004《输变电设备状态评价标准》6Q/CSG 11105.2—2008《南方电网工程施工工艺控制规范》7CSG/MS 0912—2007《电网建设工程安全和环境管理设施规范应用手册》8施工图纸9电力电缆施工手册(2002.5)10附件厂家安装说明书及技术资料3作业流程图3-1 作业(工序)流程图SDXL-ZW-13 高压电缆安装作业指导书4 安全风险辨析与预控4.1 高压电缆安装作业前,施工项目部根据该项目作业任务、施工条件,参照《电网建设施工安全基准 风险(下简称)开展针对性安全风险评估工作,形成该任务的风险分析表。
4.2 按《指/结合现场实际情况进行差异化分析,确定风险等级,现场技术员填写安全施工作业票,安全员审核,施 工4.3 施工负责人核对风险控制措施,并在日站班会上对全体作业人员进行安全交底,接受交底的作业人 员负责将安全措施落实到各作业任务和步骤中。
4.4 安全施工作业票由施工负责人现场持有,工作内容、地点不变时可连续使用 10 天,超过 10 天须重 新办理作业票,在工作完成后上交项目部保存备查。
表 4-1 作业任务安全基准风险指南1795作业准备5. 1人员配备表5-1 人员配置建议表SDXL-ZW-13 高压电缆安装作业指导书注:作业人数根据具体工程量配备。
5.2 主要工器具及仪器仪表配置表5-2 主要工器具及仪器仪表配置表序号名称规格/编号单位数量备注1手携式电锯按电压等级把22压接机100T/200T台1含工模3焊机台14煤气枪把35打磨机台36刨刀把37电吹风1000W个38手扳葫芦1T个39链条葫芦5T个310加温器台6含加温带11电烙铁把612直尺把313卡尺把314湿温计只16作业方法6. 1安装准备6. 1. 1技术资料:施工图纸、安装工艺、安技措施。