Quality Plan 质量计划中英文版

CHANGXING POWER PLANT FGD WASTEWATER PROJECT RO & THERMAL SKIDQUALITY PLAN质量计划2014.12SUZHOU SHENGDE WATER INDUSTRIES CO., LTD.苏州晟德水处理有限公司CONTENTSI Project Management Team 项目管理组织结构 ................................................................................... - 2 -1 Setup of Organization 组织机构设置 .............................................................................................. -2 -2 Responsibilities of Project Management 项目管理人员职责....................................................... - 2 - II Specification List 技术规范.................................................................................................................... - 5 - III Material Purchase 材料采购 ................................................................................................................ - 6 -1 Material Purchase and Control Plan材料采购及控制计划........................................................... - 6 -2Material Handling 材料管理.............................................................................................................. - 6 -3 Material Identification and Traceability 材料标识和可追溯性 ...................................................... - 7 - IV Quality Planning 质量策划................................................................................................................... - 8 -1 Construction Contract Explanations 施工合同交底 ...................................................................... - 8 -2 Quality Pre-control 质量预控............................................................................................................ - 8 -3 Critical Process Control 关键过程的控制 ..................................................................................... - 10 - V Inspection and Test Plan 检验检测计划............................................................................................ - 11 -1 Work List 工作列表 .......................................................................................................................... - 11 -2 Raw Material Inspection 原材料检查 ............................................................................................ - 11 -3 Frame Welding and Inspection 框架焊接与检查......................................................................... - 16 -4 Dimension Inspection 尺寸检查 .................................................................................................... - 20 -5 Sand Blasting and Inspection 喷砂与检查 ................................................................................... - 22 -6 Painting and Inspection 涂装及检查 ............................................................................................. - 24 -7 SS and CS Pipe Welding and Inspection管道焊接及检查 ........................................................ - 27 -8 Assembly Inspection 组装检查 ...................................................................................................... - 33 -9 Pressure Test 压力测试 .................................................................................................................. - 36 -10 I/O Point Test 输入输出点测试..................................................................................................... - 38 -11 Packing Inspection 包装检查 ....................................................................................................... - 39 - VI The Handling of Unaccepted Work 不合格品的处置 ..................................................................... - 42 -1 Disposal and Correcting 处置与纠正 ............................................................................................ - 42 -2 The Process Of Quality Inspection And The Final Test 质检的过程与最终检测 .................... - 42 - VII Design Changes 设计变更 ............................................................................................................... - 45 - VIII Handover of QC Documents 质检资料移交.................................................................................. - 46 -I Project Management Team 项目管理组织结构1 Setup of Organization 组织机构设置Project organizational chart refers to Appendix 1.项目组织结构图参见附件1。

2 Responsibilities of Project Management 项目管理人员职责2.1 Project Manager项目经理Main responsibilities of project manager: To carry out the contract on behalf of the company, organize and coordinate all parties to realize the overall objective of the project, control costs and ensure the time limit and quality.项目经理的主要职责:代表公司履行合约,组织并协调各方实现工程项目的总目标,控制成本,保证工期和质量。

(1) To determine the composition of project management organization and staffing, clear responsibilities of relevant personnel.确定项目管理组织机构的构成并配备人员,明确有关人员的职责。

相关主题