上人屋面施工方案(1)

世博馆工程硬泡聚氨酯喷涂板保温系统施工方案编制单位:湖南利君建工系统有限公司编制人员:方彦编制时间: 2010年2月23日目录1.工程概况_______________________________________________________________________ 5 1第1页共1.1.工程简介 ___________________________________________________________________ 51.2.工程特点 ___________________________________________________________________ 52.基本构造_______________________________________________________________________ 62.1.倒置式屋面(上人屋面) _____________________________________________________ 63.编制参考依据___________________________________________________________________ 64.机具设备_______________________________________________________________________ 7 4.1.机械、设备 _________________________________________________________________ 7 4.2.常用施工工具 _______________________________________________________________ 74.3.常用检测工具 _______________________________________________________________ 75.工艺流程及施工方案_____________________________________________________________ 8 5.1.工艺流程 ___________________________________________________________________ 82第2页共3 第 3页 共 ________________________________________________________ 8 5.2.施工方案 ___________________________________________________________________ 8 6. 人、机、料准备 _________________________________________________________________ 96.1. 材料准备 ___________________________________________________________________ 9 6.2.人员与机具准备 ____________________________________________________________ 10 7.施工技术交底 __________________________________________________________________ 10 8.申请报验 ______________________________________________________________________ 10 9. 质量要求 ______________________________________________________________________ 109.1. 工程材料质量 ______________________________________________________________ 10 9.2.工程施工质量 ______________________________________________________________ 11 10.工程验收程序 __________________________________________________________________ 1210.1.工程验收程序图: __________________________________________________________ 12 10.2.工序验收 __________________________________________________________________ 13 10.3.工程施工质量保证措施 ______________________________________________________ 1310.4.以下详细介绍成品保护的几种方法: __________________________________________ 1511.项目部人员职责________________________________________________________________ 16 11.1.项目管理框架 ______________________________________________________________ 1611.2.项目部构成人员职责 ________________________________________________________ 1612.安全文明施工管理______________________________________________________________ 17 12.1.安全管理方针及目标 ________________________________________________________ 18 12.2.安全管理体系 ______________________________________________________________ 18 12.3.安全生产管理内容 __________________________________________________________ 18 12.4.文明施工措施及实施细则 ____________________________________________________ 18 12.5.火灾的应急措施 ____________________________________________________________ 19 12.6.触电事故应急措施 __________________________________________________________ 2012.7.高处坠落事故应急措施 ______________________________________________________ 2113.劳动组织______________________________________________________________________ 21 13.1.材料计划 __________________________________________________________________ 2113.2.进度计划 __________________________________________________________________ 2114.场地布置______________________________________________________________________ 214第4页共1.工程概况1.1.工程简介1.1.1工程名称:莱茵半岛住宅小区三期1.1.2工程地点:临汾市尧都区东郊莱茵半岛住宅小区三期1.1.3建设单位:陕西中豪建设集团有限公司1.2.工程特点5第5页共2.1本工程为框架结构。

2.基本构造2.1.倒置式屋面(上人屋面)3.编制参考依据GB 50404-2007 硬泡聚氨酯保温防水工程技术规范GB/T 8624-2006 建筑材料燃烧性能分级方法6第6页共GB/T 6343-1995 泡沫塑料和橡胶表观(体积)密度的测定GB/T 3399-1982 塑料导热系数试验方法护热平板法GB/T 8811-2008 硬质泡沫塑料尺寸稳定性试验方法GB/T 6342 泡沫塑料与橡胶线性尺寸的测定GB 8810-2005 硬质泡沫塑料吸水率的测定GB/T 17671-1999 水泥胶砂强度检验方法JGJ 144-2004 外墙外保温工程技术规程JC/T 841-1999 碱玻璃纤维网格布JC/T 547-2005 陶瓷墙地砖胶粘剂QB/T 3897-1999 镀锌电焊网4.机具设备4.1.机械、设备脚手架、裁切机、手提式搅拌器、垂直运输机械、水平运输手推车等办公设备。

4.2.常用施工工具冲击钻、电锤、手提式云石机、、铝合金靠尺、托盘、锤子、改锥、橡皮锤、硅酮胶及胶枪、墨斗、刮刀、勾缝器具等。

4.3.常用检测工具专用检测工具、放线工具、水桶、剪子、钳子、扫帚、壁纸刀、托线板、方尺、靠尺、探针、钢尺等。

7第7页共5.工艺流程及施工方案5.1.工艺流程5.2.施工方案5.2.1.找坡处理5.2.1.1.1:8水泥膨胀珍珠岩,抗压强度不小于0.3MPa。

5.2.1.2.屋面坡度应不小于2%,檐沟及天沟的坡度应不小于1%,其沟底水落差不得超过200mm。

5.2.2.找平处理5.2.2.1.材料及厚度:找平层材料为1:3水泥砂浆,20mm厚,砂浆中应掺入聚丙烯或尼龙-6纤维750-900g/m3。

5.2.2.2.分格缝:找平层应设分格缝,间距宜为3-4m,分格缝面积宜为12m3左右。

8第8页共找平层养护须充分,但应避免采用大量浇水或蓄水的养护方法。

5.2.3.防水处理5.2.3.1.确定防水等级;5.2.3.2.卷材屋面和铺设方法有空铺法、点粘法、条粘法和满粘法,提倡优先采用空铺法、点粘法和条粘法。

当有条件时可在个体工程设计中交代。

5.2.3.3.防水层做法应根据设计要求等级,选择使用不同的防水层做法;5.2.4.挤塑板安装固定5.2.4.1.挤塑板安装牢固齐整,表面安装平整;5.2.4.2.板缝处采用单组份聚氨酯发泡胶密封;5.2.4.3.与结构有效粘结固定;5.2.4.4.承载力符合要求5.2.5.保护饰面层5.2.5.1.在铺设好的聚氨酯喷涂板上干铺一层无纺聚酯纤维布,交接缝搭接不小于100mm。