当前位置:
文档之家› DELL机架式服务器导轨安装图释
DELL机架式服务器导轨安装图释
3.
Repeat steps 1 and 2 for the slide assembly on the other side.
4.
Extend the inner member rails out of the rack.
Align the server's shoulder nuts with the rail's J-slots.
4.
Lift the bracket and rotate it 180 degrees counter clock wise.
5.
Line the bracket up with the two posts and set it down.
6.
Rotate the bracket clock wise until it snaps into place.
8.
Press the slide-release latch on the outside of each inner slide.
9.
Push the server towards the back of the rack.
10.
Tighten the ear nuts to secure the server to the rack.
The following procedure outlines converting the 9th generation PowerEdge rails from RapidRails to VersaRails. Converting from VersaRails to RapidRails follows the same procedure.
Server
Depth w/ CMA
Rail Compressed
Rail Extended
1950 Sliding Rapid \ VersaRail
26.98 inch
29.5 inch
2950 Sliding Rapid \ VersaRail
26.84 inch
29.46 inch
Rail Conversion
NOTE:
The rail in the example is a PowerEdge 1950 rail. The PowerEdge 2950 rails follow the exact same conversion process.
9th Generation Rail Conversion
1.
Push the front slide assembly mounting hook into the square hole on the vertical rail.
2.
Push the rear slide assembly mounting hook into the square hole on the vertical rail.
Racking
The following procedure outlines the process of racking the PowerEdge 2950 using the new 9th generation PowerEdge rails.
Racking the PowerEdge 2950
6.
Lower the server into the rails making sure the all shoulder nuts slide into the rail j-slots.
7.
Gently push the server towards the back of the rack to engage the j-slot locking levers.
1.
Locate the rail conversion bracket on the end of the rail.
2.
Lift the release lever on the rotating mounting bracket.
3.
Rotate the bracket counter clock wise.