当前位置:文档之家› 分包商合同终止会议-会议纪要-英文版

分包商合同终止会议-会议纪要-英文版

MINUTES OF SECOND SITE MEETING

--Of The Special Committee

Date: October 20th, 2012

Time: 12:00-16:30

I. Venue: Site Office OfMaseed

II. AttendeeOf The Meeting

A. Consultant:

◆Mr. XXX—Deputy R.E.

◆Mr. XXX—Inspector

B. Main Contractor:

◆Mr. XXX—Project Manager

◆Mr. XXX—Office Administrator

C. Sub-Contractor:

◆Mr. XXX-- Project Manager

◆Mr. XXX—Accounting Manager

◆Mr. XXX—Surveyor

◆Mr. XXX—Material Engineer

III. Main Issues Of The Meeting

A. The Site Works

a. Consultant:

The Deputy R.E. of the Consultant, Mr. XXX declares that the second Site Meeting Of The Special Committee start at 12:00 in the morning and welcome all the attendee of the Meeting.

Mr. XXX firstly gives a general introduction about the Project and the Remaining Issues after the first Site Meeting of The Special Committee and then he requests the Sub-Contractor gives detailed information about the works on the site and the progress of the rectification since last Meeting. b. Sub-Contractor:

The Project Manager Of the Sub-Contractor, Mr. XXXputs forward the list of Status On Site according to the requirements of the Consultants and states that they have completed all the under processing works on the site and rectified all the defects that have been remarked during the inspection of last Site Meeting.

c. Main Contractor:

The Project Manager Of The Main Contractor, Mr. XXX points out that there still exist some defects in the works of the Sub-Contractor after hearing about the statements of Mr. XXX. For example, there is one check point (K139+900) less 5cm than the specification for the Top Embankment and there still exist some weeds on the road surface from K124+000 to K129+000 ect. However, the Main Contractor still can accept the works that have been handed over to him.

B. The Works From K141+000 To K145+000

a. Consultant:

The Deputy R.E. of the Consultant, Mr. XXX states that though the Sub-Contractor has completed the works for the Clearing and Grubbing, Stripping and NGL Compaction for the section from K141+000 to K145+000 before, all the area has grown up lots of grasses again. Therefore, all the works that have been done should be repeated again. However, the Main Contractor still could give some allowance for the works that have been done by the Sub-Contractor.

b. Main Contractor:

After some consulting with the Consultant and the Sub-Contractor, the Main Contractor finally agrees with that all the works done in the section from K141+000 to K145+000 should be paid by 50% of itsOriginal Quantities, including the Clearing & Grubbing, Stripping and NGL Compaction.

C. Service Road From K141+000 To K143+000

a. Sub-Contractor:

The Project Manager Of the Sub-Contractor, Mr. xxx states that the Sub-Contractor has constructed the Service Road from K141+000 to K143+000 additionally and requested some compensation from the Main Contractor.

b. Main Contractor:

The Main Contractor refuses the request of the Sub-Contractor and states

相关主题