关垭子隧道 专项施工方案
2 目 录
1.工程概况 ..................................................................................................................................................... 1
1.1 隧道概况 ..................................................................................................................................................... 1
1.2 地质情况 ..................................................................................................................................................... 1
1.3 水文地质条件 ............................................................................................................................................. 1
2.编制依据 ..................................................................................................................................................... 1
3.施工计划 ..................................................................................................................................................... 2
3.1 施工进度计划 ............................................................................................................................................. 2
3.2 主要技术参数 ............................................................................................................................................. 2
3.3 工期计划 ..................................................................................................................................................... 2
3.4 材料计划 ..................................................................................................................................................... 3
3.5 设备计划 ..................................................................................................................................................... 3
4.施工工艺技术 .............................................................................................................................................. 4
4.1 总体施工方案 ............................................................................................................................................. 4
4.2 洞身开挖 ..................................................................................................................................................... 5
4.3初期支护与辅助工程措施 .......................................................................................................................... 6
4.4钻爆设计 .................................................................................................................................................... 14
5. 施工安全保证措施 ...................................................................................................................................17
5.1监控量测 .................................................................................................................................................... 17
5.2 超前地质预报 ........................................................................................................................................... 23
5.3 安全保证措施 ........................................................................................................................................... 23
5.4安全技术交底 ............................................................................................................................................ 25
5.5防坍塌应急预案 ........................................................................................................................................ 35
6.施工节能减排措施 .....................................................................................................................................36
6.1 节能减排施工原则 ................................................................................................................................... 36
6.2 管理体系 ................................................................................................................................................... 37
6.3 管理内容 ................................................................................................................................................... 37
6.4 节材与材料 ............................................................................................................................................... 37
7.劳动力计划 ................................................................................................................................................39
8.计算书及相关图纸 .....................................................................................................................................40
关垭子隧道 专项施工方案
1 关垭子隧道软弱围岩段专项施工方案
1.工程概况
1.1 隧道概况
隧址所在地隶属位于竹溪县蒋家堰镇,隧道洞轴线走向方位角起点274°、止点285°。左幅隧道起讫桩号均为ZK227+945~ZK229+573.587,长1628.587m,左幅最大埋深170m;右幅隧道起讫桩号均为YK227+945~YK229+571.587,长1626.587m,右幅最大埋深152m。隧道穿过3座山体。
关垭子隧道ZK229+120~ZK229+450为Ⅳ级围岩、ZK229+450~ZK229+568为Ⅴ级围岩, YK229+050~YK229+470为Ⅳ级围岩、YK229+470~YK229+566为Ⅴ级围岩,目前左线掌子面里程ZK229+363,右线掌子面里程为YK229+347,揭露围岩情况与设计不符,现场判别为Ⅴ级围岩,本方案主要针对ZK229+363~ZK229+450、 YK229+347~YK229+470软弱围岩段专项施工方法。
1.2 地质情况
隧址区属于竹溪褶皱束,该褶皱束位于北大巴山加里东褶皱带的北部,从西至东所涉及的地层主要为志留系,弱风化片岩,埋深较浅,节理裂隙较发育,岩体破碎,为硬质岩。地下水出水状态为点滴状。BQ/[BQ]=297/[277]。
1.3 水文地质条件
所经区域属汉江流域,路线所经区域的主要河流有竹溪河。其它为山涧溪流,水量受本区域季节性降雨影响,夏季水量较大、秋冬季水量小。地下水为孔隙潜水、上层滞水、构造裂隙水和基岩裂隙水,主要是受大气降水补给。
2.编制依据
1、湖北省谷城至竹溪高速公路一期土建工程施工招标《招标文件》第7篇《技术规范》及补充专用条款。;
2、中交第二公路勘察设计研究院编制的《谷城至竹溪高速公路两阶段施工图设计》;
3、施工合同及标前会议精神、补遗书;现场调查的有关资料;
4、国家及交通部现行有关设计、施工规范、验收规范、标准、规程、定额等.
《公路工程国内招标范本》( 2003版 )
《公路工程技术标准》(JTG B01-2003)
《公路隧道施工技术规范》(JTJ F60-2009)