5.1 现场布置5.1 Site Layout5.1.1项目组织机构图5.1.1 Project Organization Chart5.1.2组织机构说明5.1.2 Introduction of Organization根据本工程的特点,本着“精干、高效”的原则组建南苏丹Magwi-Lobone公路项目部,项目经理为项目的第一责任人。
In accordance with features of the project and under the principle of “high capability and efficiency”, establish the Southern Sudan Magwi-Lobone Highway Project Department, and the project manager is the primary person in charge of the project.项目部下设:The Project department comprises:◆决策层:项目经理、项目副经理、总工程师;◆Decision-making level: Project Manager, Deputy Project Manager, General Project Engineer;◆管理层:施工部、技术部、合同部、财务部、QHSE部、机物部、行政部;◆Management level: Construction Dept., Technology Dept., Contract Dept., Financial Dept., QHSE Dept., Mechanical Materials Dept., Administration Dept.;◆工区作业层:根据本工程特点,按照工区管理作业队及班组的形式。
设置4个工区,即土方一工区、土方二工区、路面工区、综合工区。
◆Work area operation level: in accordance with features of the project and as per work area’s form to manage operation teams and groups, set up 4 work areas, namely Earthwork area I, Earthwork area II, Road pavement area, Complex processing area.5.1.3主要管理层的主要工作内容及职责5.1.3 Main Work Content and Duties of Main Management Level施工部:负责施工现场的调度及生产组织等。
负责测量队的归口管理及协调工作。
◆Construction Dept.: be responsible for scheduling of construction site and organization of production, etc. In charge of the centralized management and coordination work of Survey Team.测量队:负责本项目测量控制网建立、地形地貌测绘,施工现场测控、结算测量以及竣工测量等工作。
Survey Team: be responsible for the establishment of surveying control network and geographic and geomorphic surveying and mapping of the project, construction site survey and control, settlement survey and final survey, etc.◆技术部:负责工程的施工方案和施工技术措施的编写,施工图纸的设计,进度的编制及进度更新等工作。
◆Technology Dept.: be responsible for the compilation of construction scheme and construction technical measure of the project, design of construction drawings, compilation of schedule and schedule update, etc.◆QHSE部:负责工程质量控制管理,各工序施工终检、验收,竣工资料整编等。
负责施工安全管理、爆破安全、交通安全管理、施工人员健康、消防、保卫、施工区环境保护等。
负责实验室的归口管理及协调工作。
◆QHSE Dept.: be responsible for the project’s quality control management, final inspection and acceptance of construction of all processes, reorganize completion data, etc. In charge of construction safety management, blasting safety, traffic safety management, health of construction personnel, fire control, security, construction area environmental protection, etc. In charge of the centralized management and coordination work of Laboratory.◆实验室:负责本项目原材料检测、土工试验、混凝土现场实验、沥青混凝土实验任务以及外送委托实验任务等内容等。
◆Laboratory: be responsible for material test, soil test, concrete field experiment, asphalt concrete experiment task and outside entrustedexperiment task and other content of the project, etc.◆合同部:负责合同管理、工程结算、资金流控制、预算编制等。
◆Contract Dept.: be responsible for contract management, project settlement, fund flow control, budgeting, etc.◆财务部:负责成本管理、成本控制、内部经营及负责项目部的内、外财务运作及管理等。
◆Financial Dept.: be responsible for cost management, cost control, internal operation and in charge of internal and external financial operation and management of the Project Department, etc.◆机物部:负责设备、物资、施工材料、设备配件供应及物供合同的管理,项目部仓储系统的管理,施工设备运行及修理的管理。
◆Mechanical Materials Dept.: be responsible for supply of equipment, material, construction material, equipment accessories and management of material supply contract, management of the Project Department’s storage system, and management of the operation and repair of construction equipment.◆行政部:负责文件收发、档案管理,内部行政事务,对外协调;负责后勤服务;负责项目的人力资源招聘及管理等。
◆Administration Dept.: be responsible for receiving and sending files, archives management, internal administrative affairs and external coordination; in charge of logistics service; in charge of the human resource recruitment and management of the project, etc.◆一工区:包括2个路基作业队,1个结构物作业队和1个排水作业队。
负责0+000-40+000段的清表、土石方开挖回填、排水沟、涵洞、桥梁的施工管理。
◆Work area I: includes 2 subgrade construction teams, 1 structure construction team and 1 drains construction team. Be responsible for surfacecleaning, earth-rock excavation and backfill, and construction management of drain, culvert and bridge from 0+000 to 40+000 section.◆二工区:包括2个路基作业队,1个结构物作业队和1个排水作业队。
负责40+000-811+000段的清表、土石方开挖回填、排水沟、涵洞和桥梁的施工管理。
◆Work area II: includes 2 subgrade construction teams, 1 structure construction team and 1 drains construction team. Be responsible for surface cleaning, earth-rock excavation and backfill, and construction management of drain, culvert and bridge from 40+000 to 811+000 section.◆路面工区:包括2个路面作业队。