主井皮带铺设施工问题整改治理方案

主井皮带铺设施工问题整改治理方案
(最新版)
编制人:__________________
审核人:__________________
审批人:__________________
编制单位:__________________
编制时间:____年____月____日
序言
下载提示:该文档是本店铺精心编制而成的,希望大家下载后,能够帮助大
家解决实际问题。

文档下载后可定制修改,请根据实际需要进行调整和使用,谢谢!
并且,本店铺为大家提供各种类型的安全管理制度,如通用安全、交通运输、矿山安全、石油化工、建筑安全、机械安全、电力安全、其他安全等等制度,想了解不同制度格式和写法,敬请关注!
Download tips: This document is carefully compiled by this editor. I hope that after you download it, it can help you solve practical problems. The document can be customized and modified after downloading, please adjust and use it according to actual needs, thank you!
In addition, this shop provides you with various types of safety management systems, such as general safety, transportation, mine safety, petrochemical, construction safety, machinery safety, electrical safety, other safety, etc. systems, I want to know the format and writing of different systems ,stay tuned!
主井皮带铺设施工问题整改治理方案
1、我矿主井皮带机,井下部分的全部机架已经安装完成,钢丝绳芯胶带已经到货半年多了,由于煤矿处于停产整顿阶段,皮带一直未进行硫化和敷设。

2、由于皮带属于橡胶制品,目前进入夏天,在阳关下爆晒皮带已经出现蚂蚱口,如果再不铺设,将直接影响皮带的使用寿命。

3、为了保证皮带机为矿井的正常服务年限,特此申请入井10人进行皮带铺设施工。

4、为了保证皮带铺设安全施工,专门制定“皮带安装施工安全技术措施”,并专门成立皮带铺设领导小组。

(1)、组长:张东祥(矿长)
负责组织、指挥、督促、检查全面落实“皮带安装施工安全技术措施”。

(2)、副组长:苗春雨(安全副矿长)
组织职工学习,负责皮带安装施工各项安全技术措施落实和工作布置,搞好安全检查,保证皮带安装施工期间的安全生产。

(3)、副组长:矫志强、徐明凡、王文生、温敬忠
负责井下皮带铺设安装期间的具体工作安排,并负责具体布置、协调、检查等工作,并且带班入井,同工人同入井,同升井。

5、皮带安装铺设时间,计划施工工期20天,即从6月28日至7月17日。

6、“主井皮带安装施工安全技术措施“附后,请领带审批。