篇一:FIDIC EPC交钥匙工程合同条件 (中文版银皮书) 目录

1 一般规定 ................................................ ................................................... . (6)

定义 ................................................ ................................................... (6)

解释 ................................................ ................................................... (9)

通信交流 ................................................ ................................................... . (9)

法律和语言 ................................................ ...................................................

(10)

文件优先次序 ................................................ ................................................... (10)

合同协议书 ................................................ ................................................... . (10)

权益转让 ................................................ ................................................... .. (10)

文件的照管和提供 ................................................ ................................................... . (11)

保密性 ................................................ ................................................... (11)

雇主使用承包商文

件 ................................................ ................................................... . (11)

承包商使用雇主文件 ................................................ ................................................... . (11)

保密事项 ................................................ ................................................... (12)

遵守法律 ................................................ ................................................... (12)

共同的和各自的责任 ................................................ ................................................... . (12)

2雇主. ............................................... ...................................................

(12)

现场进入权 ................................................ ................................................... . (12)

许可、执照或批准 ................................................ ................................................... . (13)

雇主人员 ................................................ ................................................... .. (13)

雇主的资金安排 ................................................ ................................................... .. (13)

雇主的索赔 ................................................ ................................................... . (14)

3雇主的管

理 ................................................ ................................................... .. (14)

雇主代表 ................................................ ................................................... .. (14)

其他雇主人员 ................................................ ................................................... (14)

受托人员 ................................................ ................................................... .. (15)

指示 ................................................ ................................................... . (15)

确定 ................................................ ...................................................

(15)

4承包商 ................................................ ................................................... . (15)

承包商的一般义务 ................................................ ................................................... . (15)

履约担保 ................................................ ................................................... .. (16)

承包商代表 ................................................ ................................................... . (17)

分包商 ................................................ ................................................... (17)

指定的分包

商 ................................................ ................................................... (17)

合作 ................................................ ................................................... . (17)

放线 ................................................ ................................................... . (18)

安全程序 ................................................ ................................................... .. (18)

质量保证 ................................................ ................................................... .. (18)

现场数据 ................................................ ...................................................

(19)

合同价格 ................................................ ................................................... (19)

道路通行权于设施 ................................................ ................................................... .. (19)

避免干扰 ................................................ ................................................... (19)

进场通路 ................................................ ................................................... (20)

货物运输 ................................................ ................................................... (20)

承包商设

备 ................................................ ................................................... .. (20)

环境保护 ................................................ ................................................... (20)

电、水和燃气 ................................................ ................................................... . (21)

雇主设备和免费供应的材料 ................................................ ....................................................

21

进度报告 ................................................ ................................................... (21)

现场保安 ................................................ ...................................................

(22)

承包商的现场作业 ................................................ ................................................... .. (22)

化石 ................................................ ................................................... .. (23)

5设计 ................................................ ................................................... .. (23)

设计义务一般要求 ................................................ ................................................... . (23)

承包商文件 ................................................ ................................................... . (24)

承包商的承

诺 ................................................ ................................................... (24)

技术标准和法规 ................................................ ................................................... .. (25)

培训 ................................................ ................................................... . (25)

竣工文件 ................................................ ................................................... .. (25)

操作和维修手册 ................................................ ................................................... .. (25)

设计错误 ................................................ ...................................................

(26)

6员工 ................................................ ................................................... .. (26)

员工的雇用 ................................................ ................................................... . (26)

工资标准和劳动条件 ................................................ ................................................... (26)

为雇主服务的人员 ................................................ ................................................... . (26)

劳动法 ................................................ ................................................... . (26)

工作时

间 ................................................ ................................................... (26)

为员工提供设施 ................................................ ................................................... .. (27)

健康和安全 ................................................ ................................................... . (27)

承包商的监督 ................................................ ................................................... (27)

承包商人员 ................................................ ................................................... . (27)

承包商人员和设备的记录 ................................................ ...................................................

(28)

无序行为 ................................................ ................................................... (28)

7生产设备、材料和工艺 ................................................ (28)

实施方法 ................................................ ................................................... .. (28)

样品 ................................................ ................................................... . (28)

检验 ................................................ ................................................... . (28)

试验 ................................................

................................................... . (29)

拒收 ................................................ ................................................... . (29)

修补工作 ................................................ ................................................... .. (30)

生产设备和材料的所有权 ................................................ ................................................... . (30)

8开工、延误和暂停 ................................................ ..................................................

30

工程的开工 ................................................ ................................................... . (30)

竣工时间 ................................................ ................................................... .. (31)

进度计划 ................................................ ................................................... .. (31)

竣工时间延长 ................................................ ................................................... (32)

当局造成的延误 ................................................ ................................................... .. (32)

工程进度 ................................................ ................................................... .. (32)

误期损害赔偿费 ................................................

(33)

暂时停工 ................................................ ................................................... .. (33)

暂停的后果 ................................................ ................................................... . (33)

暂停时对生产设备和材料的付款 ................................................ .. (33)

托长的暂停 ................................................ ................................................... .. (34)

复工 ................................................ ................................................... .. (34)

9竣工试

................................................... (34)

承包商的义务 ................................................ ................................................... (34)

延误的试验 ................................................ ................................................... . (35)

重新试验 ................................................ ................................................... .. (35)

未能通过竣工试验 ................................................ ................................................... . (35)

10雇主的接收 ................................................ ...................................................

(36)

工程和分项工程的接收 ................................................ ................................................... (36)

部分工程的接收 ................................................ ................................................... (36)

对竣工试验的干扰 ................................................ ................................................... .. (36)

11缺陷责任 ................................................ ................................................... .. (37)

完成扫尾工作和修补缺陷 ................................................ ................................................... .. (37)

修补缺陷的费

用 ................................................ ................................................... (37)

缺陷通知期的延长 ................................................ ................................................... .. (37)

未能修补的缺陷 ................................................ ................................................... (38)

移出有缺陷的工程 ................................................ ................................................... .. (38)

进一步试验 ................................................ ................................................... .. (38)

进入权 ................................................ ...................................................

EPC项目总承包合同

xxxxxxxx建设项目设计、采购、施工 (EPC)总承包合同 合同编号:字号 发包人(甲方): 承包人(乙方): 业主方(丙方): 签定时间: 签定地点: 目录

第一部分合同协议书 发包人:(全称) 承包人:(全称) 业主方:(全称) 依照《中华人民共和国合同法》、《中华人民共和国建筑法》及相关法律、行政法规、招投标文件,遵循平等、自愿、公平和诚信原则,合同双方就xxxx建设项目设计、采购、施工(EPC)总承包事宜经协商一致,订立本合同。 一、工程概况 工程名称:xxxxx 工程地点:xxxxx 工程承包范围:xxxxx总承包范围及工程子项分解如下: 1、 本项目建设内容包括房屋征收工程投资、市政与配套基础设施、公益性设施(公服设施、绿化等)等,具体以政府批复的控制性详细规划为准。 2、工程子项分解 2.1、市政基础设施地下管网

2.4、发包人有权根据适用法律和乌鲁木齐经开区相关规划调整子项目数量及其建设内容,子项目数量超过±3%进行调整,应提交董事会决议通过,以达到老城区改造建设的总体要求,合同价格随子项目增减进行调整。 二、主要技术来源 按照发包人提供的技术要求,承包人自行设计 三、主要日期 合同期限:建设期36个月,实际开始工作时间以监理人发出的开工令为准。 四、工程质量标准 工程质量标准:合格 五、合同价格和付款货币 合同价格为人民币(大写)暂定为:万元,(大写)人民币元整,其中征地拆迁费万元、建筑安装工程费万元,前期费用万元。(注:本合同签约暂定价根据可研中的建安费、勘察、设计费用以及项目操作管理、咨询费为依据,最终以甲乙双方认可的决算金额为准。)。 除根据合同约定在工程实施过程中需进行增减的款项外,合同价格不作调整。 六、合同书中的词语 本合同书中有关词语的含义与合同通用条款中赋予的定义与解释相同。 七、合同生效 合同订立时间: 合同订立地点: 本合同在以下条件满足之后生效:经双方法定代表人或其授权代表签字并加盖双方合同章后生效。 发包人: (公章或合同专用章)

国际工程总承包:EPC 交钥匙合同与管理.doc

016国际工程总承包:EPC 交钥匙合同与管 理4 内容简介 《国际工程总承包EPC交钥匙合同与管理》EPC交钥匙合同模式是国际工程承包市场越来越流行的一种建设模式。《国际工程总承包EPC交钥匙合同与管理》从EPC合同的角度出发,论述了如何管理好国际EPC项目所涉及的各个方面,包括EPC、合同的形成过程、合同双方的主要义务和责任、设计管理、采购管理、施工与试运行管理、分包管理、支付管理、风险与保险管理、索赔与争端管理以及EPC项目经理和关键职员应具备的素质等。在编写结构上,首先论述国际EPC合同中的常见规定并对此进行分析,然后提出EPC承包商相应管理的要求、程序以及应重点注意的问题,并配有相关案例。《国际工程总承包EPC 交钥匙合同与管理》具有一定的理沧性和较强的应用性,对国际工程承包实践具有很强的指导性。 目录 前言 第1章绪论:国际工程建设模式与EPC总承包 1.1 国际工程建设模式 1.2 国际工程总承包模式及其发展趋势 1.3 国际工程合同的概念与类型

1.4 小结 第2章国际EPC交钥匙总承包合同的形成过程2.1 业主选择EPC承包商的原则与方式 2.2 业主选择EPC承包商的过程 2.3 EPC承包商的投标 2.4 EPC合同的谈判与签约 2.5 小结 本章附录 第3章国际EPC交钥匙总承包合同框架分析3.1 国际EPC交钥匙合同概述 3.2 国际EPC合同协议书 3.3 EPC合同条件 3.4 EPC合同中“业主的要求” 3.5小结 第4章国际EPC交钥匙工程合同双方的义务4.1 概述 4.2 业主的义务

4.3 EPC承包商的义务 4.4 小结 第5章国际EPC交钥匙工程的设计管理 5.1 设计管理概述 5.2 EPC合同下业主对承包商设计工作的控制5.3 EPC承包商内部的设计管理 5.4 小结 第6章国际EPC交钥匙工程的采购管理 6.1 采购管理概述 6.2 国际EPC合同中的采购规定 6.3 EPC承包商内部的采购管理 6.4 国际工程物资采购案例讨论 6.5 小结 第7章国际EPC交钥匙工程的施工管理 7.1 施工管理概述 7.2 EPC合同关于施工的规定 7.3 EPC承包商内部的施工管理 7.4 小结

EPC总承包合同(最新版)

项目总承包合同示范文本 项目名称: 发包方: 承包方: 签订地点: 签订日期: 第一部分合同协议书 发包人(全称) 承包人(全称) 依照《中华人民共和国合同法》及相关法律、行政法规,遵循平等、自愿、公平和诚信原则,合同双方就_____ 项目总承包事宜经协商一致,订立本合同。 一、项目概况 项目名称: 项目地点: 承包范围: 二、主要技术来源 三、主要日期 合同期限(绝对日期或相对日期): 四、质量标准 质量标准: 五、合同价格和付款货币 合同价格为人民币(大写):元。 除根据合同约定的在项目实施过程中需进行增减的款项外,合同价格不作调整。 六、本协议书中有关词语的含义与合同通用条款中赋予的定义与解释相同。 七、合同生效 合同订立时间:年月日

合同订立地点: 本合同在以下条件满足之后生效: 发包人:承包人: (公章或合同专用章)(公章或合同专用章) 法定代表人或其授权代表:法定代表人或其授权代表: (签字)(签字) 工商注册住所:工商注册住所: 企业代码:企业代码: 邮政编码:邮政编码: 电话:电话: 传真:传真: 电子邮箱:电子邮箱: 开户银行:开户银行: 账号:账号: 第二部分通用条款 第1条一般规定 1.1 定义与解释 1.1.1 通用条款,指根据法律、行政法规的规定,合同当事人在履行项目总承包合同过程中所遵守的一般性条款,由本文件第1条至第20条组成。 1.1.2 专用条款,指根据项目总承包项目的实际,对通用条款进行补充、修改和完善,并同意共同遵守的条款。 1.1.3 项目总承包,指承包人受业主委托,按照合同约定对项目的设计、采购、施工(含竣工试验)、试运行等实行全过程或设计与其他阶段的项目承包。 1.1.4 发包人,指在合同协议书中约定的,被称为发包人的当事人,包括其合法继承人和经许可的受让人。 1.1.5 承包人,指在合同协议书中约定的,被发包人接受的具有项目总承包主体资格的当事人,包括其合法继承人。 1.1.6 分包人,指接受承包人根据合同约定对外分包的部分项目或服务的,

国际交钥匙工程合同条件中-英对照

2. Conditions of Contract for EPC/Turnkey Projects(Extracts) 设计采购施工(EPC)/交钥匙工程合同条件 (节选) 4 承包商 4 contractors 4.1 承包商的一般义务 4.1 Contractor's General Obligations 承包商应按照合同设计、实施和完成工程,并修补工程中的任何缺陷。完成后,工程应能满足合同规定的工程预期目的。 The contractor shall design, execute and complete, the works in accordance with the contract, and shall remedy any defects in the works. When completed, the works shall be fit for the purpose for which the works are intended as defined in the contract. 承包商应提供合同规定的生产设备和承包商文件,以及设计、施工、竣工和修补缺陷所需的所有临时性和永久性的承包商人员、货物、消耗品及其他物品和服务。 The contractor shall provide the plant and

contractor’s documents specified in the contract, and all the contractor’s personnel, goods, consumables and other goods and services, whether of a temporary nature, required in and for this design, execution, completion and remedying of defects. 工程应包括为满足雇主要求或合同隐含要求的任何工作,以及(合同虽未提及但)为工程的稳定、或完成、或安全和有效运行所需的所有工作。 The works shall include any work which is necessary to satisfy the Employer’s requirements, or is implied by the contract, and all works which (although not mentioned in the contract) are necessary for stability or for the completion, or safe and proper operation, of the works. 承包商应对所有现场作业、所有施工方法和全部工程的完备性、稳定性和安全性承担责任。 The contractor shall be responsible for all the adequacy, stability and safety of all site

施工合同通用条款(合同示范文本)

施工合同通用条款(合同示范 文本) Contracts concluded in accordance with the law have legal effect and regulate the behavior of the parties to the contract ( 合同范本 ) 甲方:______________________ 乙方:______________________ 日期:_______年_____月_____日 编号:MZ-HT-004297

施工合同通用条款(合同示范文本) 一、词语定义及合同文件 1、词语定义下列词语除专用条款另有约定外,应具有本条所赋予的定义: 1.1通用条款:是根据法律、行政法规规定及建设工程施工的需要订立,通用于建设工程施工的条款。 1.2 专用条款:是发包人与承包人根据法律、行政法规规定,结合具体工程实际,经协商达成一致意见的条款,是对通用条款的具体化、补充或修改。 1.3发包人:指在协议书中约定,具有工程发包主体资格和支付工程价款能力的当事人以及取得该当事人资格的合法继承人。 1.4 承包人:指在协议书中约定,被发包人接受的具有工程施工承包主体资格的当事人以及取得该当事人资格的合法继承人。 1.5 项目经理:指承包人在专用条款中指定的负责施工管理和

合同履行的代表。 1.6设计单位:指发包人委托的负责本工程设计并取得相应工程设计资质等级证书的单位。 1.7监理单位:指发包人委托的负责本工程监理并取得相应工程监理资质等级证书的单位。 1.8工程师:指本工程监理单位委派的总监理工程师或发包人指定的履行本合同的代表,其具体身份和职权由发包人承包人在专用条款中约定。 1.9工程造价管理部门:指国务院有关部门、县级以上人民政府建设行政主管部门或其委托的工程造价管理机构。 1.10工程:指发包人承包人在协议书中约定的承包范围内的工程。 1.11合同价款:指发包人承包人在协议书中约定,发包人用以支付承包人按照合同约定完成承包范围内全部工程并承担质量保修责任的款项。 1.12追加合同价款:指在合同履行中发生需要增加合同价款的

第十章 fidic工程施工合同条件_secret_修正版

第十章 FIDIC工程施工合同条件 第一节 FIDIC合同条件概述 一、 FIDIC组织简介 FIDIC是“国际咨询工程师联合会”的缩写。该组织在每个国家或地区只吸收一个独立的咨询工程师协会作为团体会员,至今已有60多个发达国家和发展中国家或地区的成员,因此它是国际上最具有权威性的咨询工程师组织。我国已于1996年正式加入FIDIC组织。 二、 FIDIC合同条件简介 为了规范国际工程咨询和承包活动,FIDIC先后发表过很多重要的管理性文件和标准化的合同文件范本。目前作为惯例已成为国际工程界公认的标准化合同格式有适用于工程咨询的《业主~咨询工程师标准服务协议书》;适用于施工承包的《土木工程施工合同条件》、《电气与机械工程合同条件》、《设计~建造与交钥匙合同条件》和《土木工程分包合同条件》。1999年9月,FIDIC又出版了新的《施工合同条件》、《工程设备与设计~建造合同条件》、《EPC交钥匙合同条件》及《合同简短格式》。这些合同文件不仅被FIDIC成员国广泛采用,而且世界银行、亚洲开发银行、非洲开发银行等金融机构也要求在其贷款建设的土木工程项目实施过程中使用以该文本为基 础编制的合同条件。

这些合同条件的文本不仅适用与国际工程,而且稍加修改后同样适用于国内工程,我国有关部委编制的适用于大型工程施工的标准化范本都以FIDIC编制的合同条件为蓝本。 (一)土木工程施工合同条件 《土木工程施工合同条件》是FIDIC最早编制的合同文本,也是其它几个合同条件的基础。该文本适用于业主(或业主委托第三人)提供设计的工程施工承包,以单价合同为基础(也允许其中部分工作以总价合同承包),广泛用于土木建筑工程施工、安装承包的标准化合同格式。土木工程施工合同条件的主要特点表现为,条款中责任的约定以招标选择承包商为前提;合同履行过程中建立以工程师为核心的管理模式。 (二)电气与机械工程合同条件 《电气与机械工程合同条件》适用于大型工程的设备提供和施工安装,承包工作范围包括设备的制造、运送、安装和保修几个阶段。这个合同条件是在土木工程施工合同条件基础上编制的,针对相同情况制定的条款完全照抄土木工程施工合同条件的规定。与土木工程施工合同条件的区别主要表现为:一是该合同涉及的不确定风险的因素较少,但实施阶段管理程序较为复杂,因此条目少款数多;二是支付管理程序与责任划分基于总价合同。这个合同条件一般适用于大型项目中的部分工程。

epc交钥匙工程合同条件

epc交钥匙工程合同条件 篇一:FIDIC EPC交钥匙工程合同条件 (中文版银皮书) 目录 1 一般规定 ................................................ ................................................... . (6) 定义 ................................................ ................................................... (6) 解释 ................................................ ................................................... (9) 通信交流 ................................................ ................................................... . (9) 法律和语言 ................................................ ...................................................

(10) 文件优先次序 ................................................ ................................................... (10) 合同协议书 ................................................ ................................................... . (10) 权益转让 ................................................ ................................................... .. (10) 文件的照管和提供 ................................................ ................................................... . (11) 保密性 ................................................ ................................................... (11) 雇主使用承包商文

建设工程施工合同(2017)

建设工程施工合同 发包方: 承包方: 工程名称: 工程地点: 签约地点: 签订日期:2017年月日

建设工程施工合同 发包方(以下简称甲方): 法定代表人: 地址: 承包方(以下简称乙方): 法定代表人: 地址: 因建设装修工程需要,甲方委托乙方以包工包料方式承包广州直流技术培训基地作业安全体感中心建设装修项目工程。为明确双方责任,确保工程顺利完工,依照《中华人民共和国合同法》、《中华人民共和国建筑法》及其他有关法律、行政法规,双方在平等、自愿、公平的基础上,经协商达成并签订本合同。 一、工程概况 1、工程名称: 2、工程地点: 3、承包方式:包工包料 4、工程内容:具体工程内容和范围以满足广州直流技术培训基地验收要求为准。 二、建设工期及开、完工时间 建设工期自合同签订生效后、乙方收到图纸确认之日起 40 工作日内完工。 三、工程质量与检验 1、工程质量等级为合格,符合工程图纸及技术要求,达到国家或行业规定的质量标准。乙方保证工程成为当地优良样板工程,工程质量达不到约定的质量标准,乙方承担违约责任。

2、双方对工程质量有争议,由依法注册成立的工程质量检测机构鉴定,所需费用及因此造成的损失,由责任方承担。双方均有责任,由双方根据其责任分别承担。 3、乙方应认真按照标准、规范和设计图纸要求以及甲方依据合同发出的指令施工,随时接受甲方的检查检验,为检查检验提供便利条件。 4、工程质量达不到约定标准的部分,甲方一经发现,应要求乙方拆除和重新施工,乙方应按甲方的要求拆除和重新施工,直到符合约定标准。因乙方原因达不到约定标准,由乙方承担拆除和重新施工的费用,工期不予顺延。 5、甲方的检查检验不应影响施工正常进行。如影响施工正常进行,检查检验不合格时,影响正常施工的费用由乙方承担。 四、工程造价 1、工程含税总造价为人民币:(RMB¥:元)。 2、工程为含税总造价,工程属交钥匙工程,如有增补,费用由乙方负责。 五、付款方式 1、合同生效后支付工程预付款为总工程款的30%(即¥ 元); 2、工程完工且经甲方验收合格后,支付工程总价款60%(即: ¥元);验收后甲方开具等额增值税专用发票,以可靠方式交付甲方 3、质保期一年,一年后支付工程总价款10%(即:¥元) 4、甲方未按合同约定支付工程款,造成停工待料,施工工期相应顺延。 六、关于工期的约定 1、甲方要求比合同约定的工期提前竣工时,应征得乙方同意,并支付乙方因赶工采取的措施费用。 2、因甲方未按约定完成工作,影响工期,工期顺延。 3、因乙方责任,不能按期开工或中途无故停工,影响工期,工期不顺延。 4、因乙主材不按时提供,工期相应顺延。 5、因设计变更或非乙方原因造成的停电、停水、停气及不可抗力因素影响、导致停工8小时以上(一周内累计计算),工期相应顺延。

建设工程施工合同通用条款

建设工程施工合同通用条款 《建设工程施工合同示范文本》分为两个部分:协议书和通用条款。下面是具体内容,由出国留学网整理提供,欢迎查阅。 第一部分协议书 发包人:(全称)________________ 承包人:(全称)________________

依照《中华人民共和国合同法》、《中华人民共和国建筑法》及其他有关法律、行政法规,遵循平等、自愿、公平和诚实信用的原则,双方就本建设工程施工事项协商一致,订立本合同。 1. 工程名称:_______________________________________ 2. 工程地点:_______________________________________

3.工程承包范围 承包范围:_______________________________________________________ ____________ 4.计划工期 计划开工日期:________年________月________日

计划竣工日期:________年________月________日计划工期总日历天数________天。 5.质量标准 工程质量标准:________________________

6.计价方式与签约合同价格 本合同采用计价方式为________________ 金额:________万元人民币 ________ (小写) 7.组成合同的文件

7.1组成本合同的文件包括: (1)合同协议书及合同附件; (2)中标通知书(如果有); (3)投标函及投标函附录(如果有);

FIDIC 2017版与1999版设计-采购-施工与交钥匙工程合同条件比较分析

FIDIC 2017版与1999版设计-采购-施工与交钥匙工程合 同条件比较分析 本文编号:GLOBAL2018-24本文转自:《国际经济合作》期刊(2018年第5期) 摘要:为满足一些业主希望项目成本及工期相对确定的要求,1999年FIDIC发布了设计-采购-施工与交钥匙工程合同 条件(银皮书)。虽然该版合同条件的应用日益广泛,但由 于将大量风险分配给承包商,其风险分担的合理性在业内受到了一定质疑。2017年FIDIC发布了银皮书的第二版,在 维持原有风险分担原则基本不变的基础上,吸收借鉴了用户反馈以及国际工程的发展动向和最佳实践,强调双方权利与责任的对等以及沟通机制和质量管理的重要性。本文从风险分担机制、项目管理机制和索赔及争端解决机制三个方面,对新版银皮书的主要变化进行分析。关键词:FIDIC 银皮 书EPC国际咨询工程师联合会(Fédération Internationale des Ingénieurs-Conseils,FIDIC)于2017年12月在伦敦举办的FIDIC国际用户会议上发布了FIDIC 2017版系列合 同条件,即施工合同条件(Conditions of Contract for Construction)、生产设备和设计-建造合同条件(Conditions of Contract for Plant and Design-Build)和设计-采购-施工与交钥匙工程合同条件(Conditions of Contract for EPC

/Turnkey Projects,本文简称“17版银皮书”)。本文将对17版银皮书与1999年发布的设计-采购-施工与交钥匙工程合同条件(Conditions of Contract for EPC /Turnkey Projects,本文简称“99版银皮书”)的主要差异进行对比分析。一、17版银皮书修订背景随着项目融资的兴起,一些工程项目业主,特别是BOT(Build-Operate-Transfer)项目,业主和银行都希望在项目启动初期获得相对固定的项目投 资以及竣工日期,他们希望将更多的不确定性交给承包商承担,且愿意为此支付更多的费用以作为承包商承担风险的对价。为了适应市场的需要,1999年FIDIC发布了设计-采购-施工与交钥匙工程合同条件(Conditions of Contract for EPC/ Turnkey Projects),在该合同模式下承包商负责完成设计、设备供货、施工安装、调试开车等工作,合同采用总价模式,与FIDIC其他合同条件相比,承包商承担的工作范围更广、风险更大。99版银皮书发布后引起了很多承包商及承包商会组织的不满,在业内也受到了一些批评和质疑,一种较为普遍的观点认为该合同条件将过多的风险不合理地 分配给了承包商。虽然FIDIC提示,若使用该合同条件,招标程序应允许在投标人和业主之间就技术问题和商务条件 进行讨论,但在实际应用中,仍然有一些不满足上述条件的项目选用银皮书作为合同的通用条件,将承包商既无法合理预见、又无法合理避免或控制的风险交给承包商承担,导致

建设项目工程总承包合同(EPC)示范文本2017

GF-2017-0216 建设项目工程总承包合同 住房和城乡建设部 制定 国家工商行政管理总局

第一部分合同协议书 发包人(全称)________________________________________________________ 承包人(全称)________________________________________________________ 依照《中华人民共和国合同法》、《中华人民共和国建筑法》、《中华人民共和国招标投标法》及相关法律、行政法规,遵循平等、自愿、公平和诚信原则,合同双方就大唐盛世商务公寓、白云山、龙珠塔、半岛酒店项目工程总承包事宜经协商一致, 订立本合同。 一、工程概况 工程名称:______________________________________________________________ 工程批准、核准或备案文号:______________________________________________ 工程内容及规模:________________________________________________________ 工程所在省市详细地址:__________________________________________________ 工程承包范围:__________________________________________________________ 二、工程主要生产技术(或建筑设计方案)来源 三、主要日期 设计开工日期(绝对日期或相对日期):______________________________ 施工开工日期(绝对日期或相对日期):______________________________ 工程竣工日期(绝对日期或相对日期):______________________________ 四、工程质量标准 工程设计质量标准:_____________________________________________________ 工程施工质量标准:_____________________________________________________ 五、合同价格和付款货币 合同价格为人民币(大写):_______________ 元(小写金额: ___________ 元)。 详见合同价格清单分项表。除根据合同约定的在工程实施过程中需进行增减的款项外, 合同价格不作调整。 六、定义与解释 本协议书中有关词语的含义与通用条款中赋予的定义与解释相同

建造与交钥匙工程合同模板条件

第 1 共 31 页 FIDIC 设计-建筑与交钥匙工程合同条件 (橘皮书) 设计-建筑与交钥匙工程合同条件(第一部分通用条件)(1-3)设计-建筑与交钥匙工程合同条件(第一部分通用条件)(4) 设计-建筑与交钥匙工程合同条件(第一部分)(5-7) 设计-建筑与交钥匙工程合同条件(第一部分通用条件)(8-11)设计-建筑与交钥匙工程合同条件(第一部分)(12-13) 设计-建筑与交钥匙工程合同条件(第一部分通用条 件)(14-17) 设计-建筑与交钥匙工程合同条件(第一部分通用条 件)(18-20) 第二部分附注 第 2 共 31 页 设计-建筑与交钥匙工程合同条件(第一部分通用条件)(1-3) 1.合同 定义 1.1 在合同(如下文所定义的)中,下文定义的措词和用语,除上下文另有要求外,应具有本款给予的含义:

1.1.1 文件 1.1.1.1“合同”指本合同条件(第一与第二部分)、雇主的要求、投标书、承包商的建议书、资料表、中标函、合同 协议书(如已签订)以及其他明确列入中标函或合同协议书(如已签订)中的此类进一步的文件。 1.1.1.2“雇主的要求”指合同中包括的对工作范围、标准、设计准则(如有时)和进度打算的讲明,以及依照合同对 其所作的任何变更和修正。 1.1.1.3“标书”指承包商为了工程间雇主提出并为中标函同意的报价书。 1.1.1.4“投标书附录”指包括在投标书中已填写完的附录。1.1.1.5“承包商的建议书”指包含在合同中、随投标书一同递交的初步设计。 1.1.1.6“资料表”指包含在合同中、与投标书一同递交的信息与数据。 1.1.1.7“支付打算表”指第1.4 款中所指的打算表(如有时)。 1.1.1.8“中标函”指雇主对投标书的正式同意函。 1.1.1.9“合同协议书”指第1.5 款中所述的合同协议书(如有时)。

交钥匙总承包合同范本

【总承包合同】EPC总承包合同范本 目录 合同协议书2 第1条合同文件2 第2条工程承包形式3 第3条总承包工程范围及内容3 第4条合同价格4 第5条支付条款5 第6条开工及完工时间、竣工时间7 第7条检验7 第8条保险7 8.1 工程一切险及建筑施工机具保险7 8.2 第三者责任保险7 8.3 雇主责任险或建筑施工人员人身意外伤害保险7 第9条税费7 第10条包装运输8 第11条工程质量8 第12条工厂性能保证8 第13条违约责任及赔偿8

第14条生效日8 第15条争端的解决9 第16条代表的指定9 第17条工程监理9 第18条其他9 第19条合同执行9 合同协议书 业主:(以下简称“业主”) 承包人:(以下简称“承包人”) 签订地点: 依据《中华人民共和国合同法》的规定,业主和承包人本着平等互利的原则,在友好协商的基础上,按下述条款和条件签署本合同:第1条合同文件 1.1合同文件 下列文件将构成业主与承包人之间的合同,且每一文件都应作为合同的不可分割的一部分来进行解释: 1、合同协议书及双方商定的附件; 2、合同条款; 3、中标通知书; 4、投标书; 5、招标阶段的补遗及澄清文件; 6、招标文件补充说明; 7、招标文件; 8、其他文件。 1.2优先顺序 构成合同的文件将被认为是互为说明的。文件的优先次序如下:

1、合同协议书及双方商定的附件; 2、合同条款; 3、中标通知书; 4、投标书; 5、招标阶段的补遗及澄清文件 6、招标文件补充说明; 7、招标文件; 8、其他文件。 如果在文件中出现含糊或歧义时,业主代表将向承包人发出必要的澄清或指示。在不违反法律和行政法规的前提下,当事人可以通过协商变更本合同的内容。这些变更的协议或文件,效力高于其他合同文件;且签署在后的协议或文件效力高于签署在先的协议或文件。 第2条工程承包形式 2.1本工程采用设计、采购、施工(EPC)/交钥匙工程总承包方式。 第3条总承包工程范围及内容 3.1前期委托工作 在合同生效之前,承包人协助业主进行方案的研究工作。 3.2 工程范围 承包人应在本合同规定的工期内按本合同要求全面负责工程建设,完成包括工程设计、主要设备采购合同的履行、设备的采购、工程保险、土建施工、安装、调试、分部及整套启动试运、性能验收试验、工程达标、工程竣工验收等方面所需的所有工作和服务,并在质量保证期内承担并履行本合同规定的各项责任和义务(以下简称“服务”)。 但厂外生活福利工程、厂外运灰道路工程和业主自购自营设备不包括在服务范围内。 在不损害上述原则的前提下,承包人应负责; 自初步设计开始,进行设计、编制技术规范,选择确定供应的设备、材料、设施、工具和采用的加工工艺及技术。 3.3工程管理及工程协调 采购设备、材料、设施、机具以及其他物品。设备采购宜与业主共同协商。 把设备、材料、设施、机具以及其它货物运输到项目场地,并负责其存放、保护和保管。 实施安装及所有与机组有关的工作,包括清淤、平整项目场地、土建、安装等工作。

常见的合同通用条款中英文对照

常见的合同通用条款 GENERAL TERMS AND CONDITIONS OF CONTRACT DATED日期 CONTRACT NAME合同名称 by and between合同双方 PARTY A NAME PARTY A甲方名称 and与 PARTY B NAME PARTY B乙方名称 TABLE OF CONTENT PRELIMINARY STATEMENT前言 1. DEFINITIONS定义 2. [OPERATIVE CLAUSES] 具体操作条款 3. CONDITIONS PRECEDENT如有必要,根据交易具体情况设定相应先决条件 4. REPRESENTATIONS AND WARRANTIES 陈述和担保[保证] 5. TERM合同期限 6. TERMINATION合同终止 7. CONFIDENTIALITY保密义务

8. BREACH OF CONTRACT违约 9. FORCE MAJEURE不可抗力 10. SETTLEMENT OF DISPUTES争议的解决 11. APPLICABLE LAW 适用法律 12. MISCELLANEOUS PROVISIONS其他规定 THIS CONTRACT(“Contract”)is made in [city and province], China on this day of ,200 by and between [Party A name],[Party A entity form] established and existing under the laws of China, with its legal address at [address] (hereinafter referred to as “Party A”), and [Party B name], [Party B entity form] organized and existing under the laws of [Party Bjurisdiction of incoporation] with its legal address at [address] (hereinafter referred to as “Party B”). Party A and Party B shall hereinafter be referred to individually as a “Party ” and collectively as the “Parties”. 本合同于年月日由以下两方在[地点]签订: [甲方名称],一家根据中华人民共和国法律组建及存续的[甲方组织形式],法定地址为[甲方法定地址](以下简称“甲方”): [乙方名称],一家根据[乙方所在国]法律组建及存续的[乙方组织形式],法定地址为[乙方法定地址](以下简称“乙方”)。 甲乙双方以下单独称为“一方”,合称为“双方”。 PRELIMINARY STATEMENT 前言 [add background information if appropriate][视交易具体情况决定是否应介绍合同背景] After friendly consultations conducted in accordance with the principles of equality and mutual benefit, the Parties have agreed to [describe subject matter of the Contract] in accordance with Applicable laws and the provisions of this Contract. 双方本着平等互利的原则,经友好协商,依照[相关法律名称]以及其他有关法律,同意按

九部委EPC总包合同通用合同条款

编号:_______________本资料为word版本,可以直接编辑和打印,感谢您的下载 九部委EPC总包合同通用合同条款 甲方:___________________ 乙方:___________________ 日期:___________________

通用合同条件 1.一般约定 1.1词语定义 通用合同条款、专用合同条款中的下列词语应具有本款所赋予的含义。 1.1.1合同 1.1.1.1合同文件(或称合同):指合同协议书、中标通知书、投标函及投标函附录、专用合同条款、通用合同条款、发包人要求、价格清单、承包人建议书,以及其他构成合同组成部分的文件。 1.1.1.2合同协议书:指第1.5款所指的合同协议书。 1.1.1.3中标通知书:指发包人通知承包人中标的函件。中标通知书随附的澄清、说明、补正事项纪要等,是中标通知书的组成部分。 1.1.1.4投标函:指构成合同文件组成部分的由承包人填写并签署的投标函。 1.1.1.5投标函附录:指附在投标函后构 成合同文件的投标函附录。 1.1.1.6发包人要求:指构成合同文件组成

部分的名为发包人要求的文件,包括招标项目的目的、范围、设计与其他技术标准和要求,以及合同双方当事人约定对其所作的修改或补充。 1.1.1.7价格清单:指构成合同文件组成部分的由承包人按规定的格式和要求填写并标明价格的清单。 1.1.1.8承包人建议书:指构成合同文件组成部分的名为承包人建议书的文件。承包人建议书由承包人随投标函一起提交。承包人建议书应包括承包人的设计图纸及相应说明等设计文件。 1.1.1.9其他合同文件:指经合同双方当事人确认构成合同文件的其他文件。 1.1.2合同当事人和人员 1.1. 2.1合同当事人:指发包人和(或)承包人。 1.1. 2.2发包人:指专用合同条款中指明并与承包人在合同协议书中签字的当事人。 1.1. 2.3承包人:指与发包人签订合同协 议书的当事人 1.1. 2.4承包人项目经理:指承包人指定代表承包人履行义务的负责人。

FIDIC合同条款-设计采购施工(EPC)交钥匙工程合同条件(银皮书)

FIDIC设计-建造与交钥匙工程合同条件 (银皮书) 目录 设计-建造与交钥匙工程合同条件(第一部分通用条件)(1-3) (2) 设计-建造与交钥匙工程合同条件(第一部分通用条件)(4) (10) 设计-建造与交钥匙工程合同条件(第一部分通用条件)(5-7) (18) 设计-建造与交钥匙工程合同条件(第一部分通用条件)(8-11) (25) 设计-建造与交钥匙工程合同条件(第一部分通用条件)(12-13) (33) 设计-建造与交钥匙工程合同条件(第一部分通用条件)(14-17) (42) 设计-建造与交钥匙工程合同条件(第一部分通用条件)(18-20) (50) 第二部分附注 (59)

设计-建造与交钥匙工程合同条件(第一部分通用条件)(1-3) 1.合同 定义 1.1在合同(如下文所定义的)中,下文定义的措词和用语,除上下文另有 要求外,应具有本款赋予的含义: 1.1.1文件 1.1.1.1“合同”指本合同条件(第一与第二部分)、雇主的要求、 投标书、承包商的建议书、资料表、中标函、合同协议书(如已签订)以及其他明确列入中标函或合同协议书(如已签订)中的此类进一步的文件。 1.1.1.2“雇主的要求”指合同中包括的对工作范围、标准、设计 准则(如有时)和进度计划的说明,以及根据合同对其所作的任何变更和修正。 1.1.1.3“标书”指承包商为了工程间雇主提出并为中标函接受的 报价书。 1.1.1.4“投标书附录”指包括在投标书中已填写完的附录。 1.1.1.5“承包商的建议书”指包含在合同中、随投标书一同递交 的初步设计。 1.1.1.6“资料表”指包含在合同中、与投标书一同递交的信息与 数据。 1.1.1.7“支付计划表”指第1.4款中所指的计划表(如有时)。 1.1.1.8“中标函”指雇主对投标书的正式接受函。 1.1.1.9“合同协议书”指第 1.5款中所述的合同协议书(如有 时)。 1.1.2人员 1.1. 2.1“雇主”指投标书附录中指定的当事人以及取得此当事人 资格的合法继承人,但不指(除非承包商同意)此当事人的任何受让人。 1.1. 2.2“承包商”指其投标书已为雇主接受的当事人以及取得此 当事人资格的合法继承人,但不指(除非雇主同意)此当事人的任何受让人。

工程总承包EPC合同示范文本范本

工程总承包合同示范文本

目录 第一部分合同协议书 (2) 第二部分通用条款 (4) 第三部分专用条款 (58)

第一部分合同协议书 发包人(全称) 承包人(全称) 依照《中华人民共和国合同法》、《中华人民共和国建筑法》及相关法律、行政法规,遵循平等、自愿、公平和诚信原则,合同双方就_____ 项目工程总承包事宜经协商一致,订立本合同。 一、工程概况 工程名称: 工程地点: 工程承包范围: 二、主要技术来源 三、主要日期 合同期限(绝对日期或相对日期): 施工期限(绝对日期或相对日期): (其中:竣工日期(绝对日期或相对日期):) 四、工程质量标准 工程质量标准: 五、合同价格和付款货币 合同价格为人民币(大写):元。 除根据合同约定的在工程实施过程中需进行增减的款项外,合同价格不作调整。 六、本协议书中有关词语的含义与合同通用条款中赋予的定义与解释相同。 七、合同生效 合同订立时间:年月日 合同订立地点: 本合同在以下条件满足之后生效:____________ _________ 发包人:承包人: (公章或合同专用章)(公章或合同专用章)

法定代表人或其授权代表:法定代表人或其授权代表:(签字)(签字) 工商注册住所:工商注册住所: 企业代码:企业代码: 邮政编码:邮政编码: 法定代表人:法定代表人: 授权代表:授权代表: 电话:电话: 传真:传真: 电子邮箱:电子邮箱: 开户银行:开户银行: 账号:账号:

第二部分通用条款 第1条一般规定 1.1 定义与解释 1.1.1 通用条款,指根据法律、行政法规的规定,合同当事人在履行工程总承包合同过程中所遵守的一般性条款,由本文件第1条至第20条组成。 1.1.2 专用条款,指根据工程总承包项目的实际,对通用条款进行补充、修改和完善,并同意共同遵守的条款。 1.1.3 工程总承包,指承包人受业主委托,按照合同约定对工程建设项目的设计、采购、施工(含竣工试验)、试运行等实行全过程或设计与其他阶段的工程承包。 1.1.4 发包人,指在合同协议书中约定的,被称为发包人的当事人,包括其合法继承人和经许可的受让人。 1.1.5 承包人,指在合同协议书中约定的,被发包人接受的具有工程总承包主体资格的当事人,包括其合法继承人。 1.1.6 分包人,指接受承包人根据合同约定对外分包的部分工程或服务的,并具有相应资格的法人或其他组织。 1.1.7 发包人代表,指发包人指定的履行本合同的代表。 1.1.8 监理人,指发包人委托的具有相应资质的工程监理单位。 1.1.9 工程总监,指由监理人授权、负责履行监理合同的总监理工程师。 1.1.10 项目经理,指承包人按照合同约定任命的负责履行合同的代表。 1.1.11 永久性工程,指承包人根据合同约定,进行设计、施工、竣工试验、竣工后试验和(或)试运行考核并交付发包人进行生产操作或使用的工程。 1.1.12 单项工程,指专用条件中列明的具有某项独立功能的工程单元,是永久性工程的组成部分。 1.1.13 临时性工程,指为实施、完成永久性工程及修补任何质量缺陷,在现场所需搭建的临时建筑物、构筑物,不构成永久性工程实体的工程。 1.1.14 现场或场地,指合同约定的用于承包人现场办公、居住、设备材料部件存放、施工机具、设施存放和工程实施的任何地点。 1.1.15 项目基础资料,指发包人提供给承包人的经有关部门对项目批准或核准的文件、报告(选厂报告、资源报告、勘察报告)、资料(气象、水文、地质)、协议(燃料、水、电、气、运输)和有关数据等,设计所须的基础资料。 1.1.16 现场障碍资料,指发包人为承包人完成设计、进行现场施工所需要提供的地上和地下已有的建筑物、构筑物、须受保护的古建筑、古树木等坐标方位、数据和其他情况的资料。