目录1.编制依据............................................................................................................................ 11.1施工图纸 ............................................................................................................................ 11.2主要规范、规程................................................................................................................ 11.3施工组织设计及施工方案................................................................................................ 11.4工程概况 ........................................................................................................................... 12.施工准备 ........................................................................................................................... 22.1技术准备............................................................................................................................ 22.2现场准备 ........................................................................................................................... 32.3劳动力准备: ................................................................................................................... 33.施工部署 .............................................................................................................................. 34.施工方法.............................................................................................................................. 34.1技术要点 ........................................................................................................................... 34.2材料要求........................................................................................................................... 44.3混凝土浇筑....................................................................................................................... 45.质量保证措施 ...................................................................................................................... 85.1降低水泥水化热................................................................................................................ 85.2 降低砼的入模温度 .......................................................................................................... 85.3加强砼浇筑中的温度控制 ............................................................................................... 95.4材料控制........................................................................................................................... 95.5其他控制措施 ................................................................................................................... 96 人员分工情况................................................................................................................. 107.砼浇筑前的裂缝控制计算 .............................................................................................. 117.1进行裂缝控制计算的目的............................................................................................ 117.2计算依据及计算假定 ................................................................................................... 118.安全措施....................................................................................................................... 149.文明施工和环保措施................................................................................................... 151.编制依据1.1施工图纸北京建筑工程学院科贸楼二期工程施工图纸。
1.2主要规范、规程《建筑工程冬期施工规程》(JGJ 104-97)《混凝土结构工程施工质量验收规范》(GB250204-2002)《混凝土泵送施工技术规程》(JGJ/T10-95)《地下工程防水技术规范》(GB50108-2001)。
1.3施工组织设计及施工方案《北京建筑工程学院科贸楼二期工程施工组织设计》1.4工程概况本工程基础底板、地下室外墙、及地下邻土顶板均采用C40防水混凝土,抗渗等级P10。
底板面积约为5400m2,混凝土体积约为4200m3,分为三段,设有2条后浇带,后浇带宽度800mm。
本工程基础底板厚度为600mm底板砼为大体积砼,应重点做好防止水化热造成的温度裂缝和施工中的冷缝。
除积水坑外,底板板顶标高-15.8m,在施工方法上,底板与墙体施工缝留置在地梁顶以上200mm高的外墙部位,采用止水钢板,后浇带采用WB型橡胶止水条。
对地下室以下固定模板的螺栓必须穿过混凝土墙面时,应采取止水螺栓。
2.施工准备2.1技术准备2.1.1提前一个月的时间,对商砼搅拌站提出搅拌砼的材料要求、砼工作性、强度等级等要求,并签订商砼技术合同和服务要求。
2.1.2组织工长和外施作业队学习有关规范规定和熟悉施工图。
2.1.3编写技术交底,并对作业人员进行书面和口头交底。
2.1.4底板筋、墙插筋检查验收完毕,做完隐检记录和质评,并须经监督站、监理检查验收合格。
测温管已埋设固定好。
2.1.5墙体水平施工缝,按构造要求支模完毕,检查合格,做完预检及质评。
2.1.6标高、复核完毕,精度符合要求,轴线控制桩,高程点有保护措施。
2.1.7做完技术交底、安全交底。
2.1.8填写浇灌申请,并到搅拌站做完开盘鉴定。
2.1.9关于搅拌站准备情况一会由搅拌站的同时单独介绍2.1.10试块留置连续浇筑超过1000m³,同一配合比每200m³至少取标养试块一组。
每标段至少取样4组,(1、同条件,2、600度日3、受冻前临界强度检验,4、同转标),抗渗性能检测每500m³取样一次。
2.1.11梁、板按规范要求留置测温孔。
2.1.12浇注过程中实验员现场测塌落度、经计算混凝土出站温度不低于15°、入模温度不低于5°并做好记录。
2.1.13浇注过程中连续浇注避免出现冷缝。
2.1.14浇筑完毕后覆盖严密避免受冻。
2.1.15浇筑完成后做好测温养护工作。
2.1.16对泵管做好保温。
2.2现场准备2.2.1按现场实际确定输送泵管位置并布设好泵管。
2.2.2电源、配电箱、水管引到指定位置。
2.2.3机具准备:低噪声振捣棒13条(50规格);(2)配电箱4个;(3)照明锑灯6个;(4)橡胶水管150m;(5)铁锹20把;(6)塑料薄膜5000m2;(8)塑料薄膜5000m2;(9)2m铝合金杠尺10条,木抹子20把。