双梁桥式 (驾操)控制起重机double girder bridge-type of crane (cab operation) control使用说明书operation instruction无锡运达机械有限公司WUXI YUNDA MACHINERY CO.LTD目录CATALOGUE1.用途1 . Application2.技术特征和主要参数2 . Technical characteristics and major parameter3.结构3 .Construction3.1金属结构3. 1 Metal structure3.2 起重机运行机构3.2 Running gear of crane3.3其它设备3.3 Others Equipment4.电气控制设备4.Electric control equipment4.1凸轮控制器:4. 1 Cam controller4.1保护配电盘:4. 2 The protection switchboard:4.3主令控制器:4. 3 The master controller:4.4限位和安全开关:4. 4 Limit and safety switch5.安装、调试和试运行5. Installation, debugging and commissioning5.1安装和调试5. 1 Installation and adjustment5.1.1桥架拼装:5. 1. 2 Bridge assembly5.1.2小车安装5. 1. 2 Trolley installation5.1.3操纵室等部件安装5. 1. 3 Operating room etc installation:5.1.4电气设备安装5. 1. 4 Electrical equipment installation5.1.5钢丝绳的缠绕5. 1. 5Steel rope winding::5.2 起重机的试运行5. 2 Crane commissioning6.起重机的维护和保养6. Crane maintenance6.1机械设备的维护和保养6. 1 Mechanical equipment maintenance 6.2金属结构的维护和保养6. 2 Metal structure maintenance6.3电气设备的维护和保养6. 3 Electrical equipment maintenance 6.4安全操作注意事项6. 4 Safe operation notice1.用途1. APPLICATION本产品用于机械制造车间,仓库,料场,水电站检修,装配等场所,进行一般重装卸作业,本产品的工作环境温度为-25℃∽±45℃,不适用于爆炸危险,灾危险介质中和相对温度大于85%,充满腐蚀性气体的场所,也不适用于吊运化金属和有毒,易燃的物品This product applies to mechanical manufacture workshop, warehouse, material yard, hydroelectric plant maintenance,assembly etc for common lifting, loading or unloading works.This product working environment is -25℃∽±45℃,not applicable to explosive dangerous, fire danger carrier and relative temperature above 85%, places full of corrosive gas, nor lifting Melton metal, poisonous, flammable, explosive materials.2.技术特征和主要参数2. TECHNICAL CHARACTERISTICS AND MAJOR PARAMETER本系列桥式起重机的主要参数如下:The key parameters of this series overhead crane girder key parameter as follows2.1起重量: QD32/10T2.1 Elevating capacity: QD32/10T2.2跨度: 13.5M2.2 span: 13.5m2.3工作制度: A3(用于偶尔使用工作场所,例如装货车间)。
2.3 working systerm: A3( use for occasionally workplace, such as assembly workshop)按确定的起重量、跨度和工作制度,可查阅随机附加的桥式起重机总图和小车图纸中的技术特性表和需要的外形尺寸参数。
Base for certain elevating capacity,span and work systerm , handlers can look upthe general drawing of the overhead crane girder, list of technical characteristic in the drawing of the trolly and needed outline dimensional parameters起重量用分数表示时,分子表示主起升重量,分母表示副起升重量。
While elevating capacity use fraction represent, molecule repersent the major elevating capacity, denominator represent deputy elevating capacity.3. 结构3. CONSTRUCTION整台起重机是由桥架、小车(装有起升机构和运行机构)、起重机运行机构和电气设备四大部分组成。
The whole crane girder is consist of four parts : crane span structure, trolly( with hoist gear and running gear), the running gear of crane and electric equipments起升机构、小车运行机构和起重机运行机构是起重机的三个工作机构,各机构都备有单独的电动机,进行各自的驱动。
Hoist gear ,the running gear of crane and the running gear of crane are three working gear of crane, each gear has indvidual electromotor can do respective driving32/10吨的起重机,具有两个吊钩,因此有主、副两套独立的起升机构。
主钩用来提升重的物件,副钩除可提升较轻的物件外,在它额定的负荷范围内也可用来协同主钩倾转或翻倒工件之用。
但必须注意的是,不允许两个吊钩同时提升两个物件。
两个吊钩一起工作时,物件的重量不许超过主钩额定起重量本起重机共有二套起升机构。
,所吊运的物件重量不应超过起重机的额定起重量,每个吊钩只可起吊该吊钩的额定起重量。
The 30/10 ton cranhas two lifting hook, therefore,it has main and deputy in total two hoist gears. The main lifting hook use for lift heavy article, besides the deputy lifting hook use for lift lighter article, it also can use for helping main hook to vert or turnover article in its rated range of load. However, it should pay attention to not allow lifting two articles with two hooks in the same time. If two hooks are working in the same time, the weight of article should not exceed rated range of load of the main hook.This crane has two hoist gears. The weighgt of swing article should not exceed rated range of load of the crane, each hook only can lift its rated range of load.3.1金属结构3.1 METAL STRUCTURE金属结构包括桥架、小车架和操纵室。
桥架是由两根箱形主梁、两根箱形端梁和主梁两侧的走台所组成。
在主梁的上盖板上铺设轨道,供小车行走之用。
与主梁连接的一侧走台上安装起重机的运行机构。
另一侧走台安装小车导电的滑线。
走台的外侧都有栏杆,以保障检修人员的安全。
Metal structure is consists of crane span structure, trolly frame and handingroom.Crane span structure is consist of two pieces of box-type girders , two pieces of girders and on both sides of the runway. On the main girder lay track on upper cover plate in order to for the car to walk. One side of the walking aborad connected to the main girder crane install running gear. The other side of swaliking aborad install slide wire for electric. Both sides of walking aborad have rails to ensure the safety of the maintenance staff.主梁与端梁进行刚性联接,两根端梁的中部是用螺栓连接起来的可拆件。