Training Purpose/培训目的
•Let suppliers have a initial understanding of Volvo vehicle development process
给供应商一个有关沃尔沃产品开发流程的简单介绍•Let suppliers understand all the activities which relate to suppliers
让供应商理解所与供应商有关的活动
Issue date: 2/15/2012
GPDS/GPDS 的定义
•GPDS: Global Product Development System •GPDS :全球产品开发体系
Issue date: 2/15/2012
•GPDS get the engineering, design, purchasing, manufacturing , marketing (customer) and suppliers to work together to deliver a good vehicle.
•GPDS将工程,造型,采购,制造,市场和供应商整合在一起,为客户开发一个好的车型。
Issue date: 2/15/2012
Powertrain / 动力总成Under body / 下车体Upper body /上车体
Issue date: 2/15/2012VPP (supplier related)/供应商相关的VPP
Issue date: 2/15/2012
VPP (supplier related)/供应商相关的VPP
•PS (Program start)
项目开始
•PSC (Program strategy confirmation)
项目策略确定
•PTCC (Program Target Compatibility Check point)项目目标分解
•PTC (Program Target Confirmation)
项目目标确定
Issue date: 2/15/2012
•PA (Program Approval)
项目批准
•LR (Launch Readiness)
投产准备就绪
•LS (Launch Sign Off)
投产签收
•J1 (Job1)
量产
VPP (supplier related)/供应商相关的VPP
Issue date: 2/15/2012
Builds/装车活动
M1 build
M1 build is to verify under body. So under body related parts are affected.
M1装车是为了验证下车的设计,所以只有下车体的零件影响到。
L421 program already finished the M1 build. All related parts have been provided by related suppliers.
L421 项目的M1装车活动已经结束,所有相关零件已经有各个供应商提供。
Issue date: 2/15/2012
Builds/装车活动
E3/E4 build / E3/E4装车
E3/E4 build is to verify electrical parts’function (no dimension requirement). All body electrical parts are affected. Chassis and PT electrical parts are not affected.
E3/E4装车是为了验证车身电子零件的性能(对几何尺寸没有要求),车身电子相关零件需要支持该装车。
底盘和动力系统的电气相关的零件不需要支持。
Support needed from suppliers/需要供应商支持-Provide qualified parts on time/准时提供合格零件-On site support the builds for key parts/关键零件供应商现场支持装车。
-Resolve the issue found in the builds/解决装车问题
Issue date: 2/15/2012
MTO Build (Machine Try Out Build)
MTO build is to verify BIW (body in white) and body shop process. All stamping parts are affected. No any trim parts are needed. Build will only in body shop. Parts must be from job1 tooling. This build is before VP
MTO 是为了验证白车身和焊装工艺的一次装车,只在焊装车间进行,只有冲压件会影响到,总装零件不需要支持。
所有零件必须是量产模具制作的。
MTO 装车发生在VP 装车之前。
Support needed from suppliers/需要供应商支持-Provide qualified parts on time/准时提供合格零件-On site support the builds for key parts/关键零件供应商现场支持装车。
-Resolve the issue found in the builds/解决装车问题Builds/装车活动
Issue date: 2/15/2012PCF Definition/PCF 定义
PCF: Body Parts Coordination
PCF: 焊装零件几何尺寸检查
PCF Methods/TPC 方法
Use fixtures to simulate standard body then check the body parts dimension.
用检具来模拟标准车身,以此来检查焊装零件的几何尺寸。
PCF Plan
Refer to VPP
参考VPP
PCF Related Parts/PCF 相关零件
All body parts
所有焊装的零件
Builds/装车活动
Issue date: 2/15/2012
Support needed from suppliers of PCF/需要供应商支持
1.Provide the parts in time
及时提供样品
2.Provide the date of the sample parts
按要求提供样品的检测数据
3.Arrange the engineers to be in Chengdu plant when the PCF build happens
安排工程师到场参与PCF 的建造
4.Take actions for the issues which are found in the PCF builds
采取改善行动来改善PCF 所发现的问题
Builds/装车活动
Issue date: 2/15/2012Support needed from suppliers of TPC/需要供应商支持
1.Provide the parts in time
及时提供样品
2.Provide the date of the sample parts
按要求提供样品的检测数据
3.Arrange the engineers to be in Chengdu plant when the TPC build happens
安排工程师到场参与TPC 的建造
4.Take actions for the issues which are found in the TPC builds
采取改善行动来改善TPC 所发现的问题
Builds/装车活动。