START UP AND MAINTENANCE INSTRUCTIONS FORSHATOMIZER :喷雾器启动及维护手册TABLE OF CONTENTS目录1 START UP OF SHATOMIZER 启动喷雾器1.1Installation cold state / first start up 冷状态安装/首次启动1.2Start up after standstill 停止后再启动1.3Action temporary standstill 暂停启动1.4Withdrawing shatomizer from use 使用状态中撤下喷雾器1.5Replacing shatomiser 喷雾器的更换2 SETTINGS 装置配备2.1 Electrical cabinet: 电气柜2.1.1 Vibro Check稳定性检查2.2 Mechanical cabinet: 机械柜2.2.1 Oil-air lubrication unit 油气润滑单元2.2.2 pressure monitoring device primary cooling 压力监控装置初始冷却2.2.3 Heating element 加热装置2.2.4 Pressure reducing valve 减压阀2.2.5 Manual temperature control valve on secondary cooling circuit第二阶段冷却循环手动温控阀3 MAINTENANCE 维护3.1 Maintenance维护3.1.1 Shatomizer / Spray-disc 喷雾器/喷雾盘3.1.2 Mechanical cabinet 机械柜3.1.2.1 General 概述3.1.2.2 Secondary water filter 二次水过滤3.1.2.3 Filter in reducing valve secondary water 二次水过滤减压阀中的过滤器3.1.2.4 Temperature-controlled valve in secondary water pipe 二次水循环管中的温控阀3.1.2.5 Oil-lubrication unit 注油单元3.1.2.6 Cooling air fan for shaft 传动轴空气冷却风扇3.1.2.7 Cooling pumps for primary cooling system 基本冷却系统冷却泵3.2 Data sheets 相关数据3.2.1 Intervention report shatomizer 喷雾器干预报告3.2.2 Shatomizer filing card 喷雾器存档实用卡片1 START UP OF SHATOMIZER1 喷雾器启动1.1 INSTALLATION COLD STATE / FIRST START UP:1.1冷状态安装/首次启动1) Place shatomizer in wait position placed closest to the shaft将喷雾器放置在离传动轴最近的地方2) Cover in hoist. 置于起重机下方3) Connect couplings on shatomizer in following order: 按以下顺序联接各部件- Connect steel lifting cable 联接起吊钢丝绳- Power plug 电源电缆插头- Control plug 控制电缆插头- Cooling water in 冷却水进水- Cooling water out 冷却水回水- Lime milk / and water 石灰乳/和水- Sealing air 密封空气- Removal of closing coupling oil lubrication and place on the holderProvided 卸除油润滑装置隔离联接器,放在底座上- Installation of oil lubrication coupling 安装油润滑装置联接器。
4) Remove closing cover on the shaft. 移除传动轴的隔离罩5) Place shatomizer in shaft 将喷雾器置于传动轴上6) Connect all couplings on cover in the same order as described above,with the exception of the steel cable. 同样按照以上顺序联接除钢帘线以外的盖罩的所有部件。
7) reset Vibro Check in electrical cabinet 在电气柜中复位震动仪。
8) Place switch electrical cabinet to manual 将电气柜开关设置为手动9) Give release cooling air fan 打开空气冷却扇10) Place switch electrical cabinet on local auto 将电气柜开关设置为本地自动11) Give release PU 释放PU-If the temperature of the primary water is less than 28°C, theheating starts to operate Switching operation ON – 28°C – 32°C –OFF如果初始水温低于28°C,加运行热开始(28°C开 32°C关)-When the temperature of the bearings has reached 20°C, thecompressed air valve of the lubrication unit opens, this is protected viathe program. Further operations are not possible until this temperaturehas been reached.如果轴承的温度达到20°C,润滑单元气压阀启动,这是程序设置的保护程序。
如果未达到这个温度,将不会进行进一步的程序。
Then the lubrication unit starts to operate, and the PLC activates theoil pump at certain times. If you wish to achieve optimal oil-airoperation in the pipes, it is recommended to already activate this 48hours before the appliance starts to operate. You can accelerate thisperiod by regularly manually activating the pump (manual run).然后润滑单元启动,PLC将在特定的时间激活油泵。
如果想使管道内的油气运行达到最佳状态,推荐在本设备开始运行前48小时激活。
12) Check of all settings (oil lubrication pressure, sealing air pressure,General air pressure, flow rate of sealing air).检查所有的装置(油润滑压力,空气密封压力,一般空气压力,空气密封气流)Before starting up, it is recommended to make a complete check ofAll settings (see settings sheet).在本设备启动前,推荐进行全面的部件检查(见第二章部件)Visual check of the oil-air flow. 目检油气流动情况。
13) Adjusting speed. 调整速度The speed used is 10,000 revs./min. Depending on the process, thiscan vary to a maximum of 12,000 revs./min.使用速度10000转/分钟。
根据运行情况,可调整的范围最大为12000转/分钟。
14) Resetting of all alarms 所有的警报复位15) Appliance is ready to be started. 本设备整机待命,等待启动。
16) When heating the installation, ACTION TEMPORARY STANDSTILLis initiated. 本设备安装过程中,设置为暂停静止状态。
1.2 START UP AFTER STANDSTILL: 暂停结束,开始启动NOTE: Cooling air fan is still rotating, PU still released.注意:冷风扇仍在转动,电源处于接通开启动状态。
1)Place shatomizer in wait position placed closest to the shaft.将喷雾器置于离传动轴最近的等候区域。
2)Cover in hoist.置于起重机下方。
3)Connect couplings to shatomizer in following order: 按以下顺序联接各部件- Connect steel lifting cable 联接钢帘线- Power plug 连接开关- Control plug连接控制开关- Cooling water in 冷水输入- Cooling water out冷水输出- Lime milk / and water石灰乳/和水- Sealing air 空气密封- Removal of blocking coupling oil lubrication and place on holder卸除油润滑装置隔离联接器,放在底座上- Installation of oil lubrication coupling 安装油润滑装置联接器。
4)Remove closing cover on the shaft 移除传动轴的隔离罩5)Place shatomizer in shaft 将喷雾器置于传动轴上6)Connect all couplings on cover in the same order as described above with theexception of the steel cable.同样按照以上顺序联接除钢丝绳以外的盖罩的所有部件。