Conditions Of Contract
Index
1)Definitions
2)Inspection of Site
3)Time for Completion
4)Liquidated and Ascertained Damages
5)Payment
6)Defect Liability Period
7)Employer's and Building Owner's Indemnity
8)Insurance Against Injury to Persons and Property
9)Insurance of the Works Against fire, etc
10)Insurance Against Injury of Workmen
11)Statutory Obligations
12)Variations
13)Water and Electricity Supplies
14)Avoidance of Nuisance Due to the Works
15)Programmer of Works
16)Termination of the Contract
17)Design, Materials and Workmanship
18)Tests
19)As-Build Drawings and Records
20)Contractor's obligation
21)Correspondences
Conditions Of Contract
1)DEFINITIONS
For the context of this contract, the following terms shall have the definitions as below:
Building Owner :All legal owners and/or Incorporated Owners of
the Premises
Employer : China Merchant Americold Ltd
Contractor : The person, firm or company appointed to
carry out the Works of this contract including
his heirs, executors or administrators.
Premises : Hutchison Logistics Centre, Container Port 4,
Kwai Chung
The Works : All works required as stipulated in the cope of
Works, Specification, Drawings and Schedule
of Rates in relation to this Contract.
2)INSPECTION OF SITE
The Contractor is required to visi (the site and verify the exact scope, nature and quality of the Works including all relevant information included in this document and allow all necessary for the carrying out of the Works in the Tender sum. Site visit can be arranged by advance appointment with the Project Manager.
3)TIME FOR COMPLETION
a)The anticipated Date for Commencement and Date for
Completion of the Works are late November 2012 and before End of February 2013)but is subject to written confirmation by the Employer. No adjustment to the Contract Sum will be made if the date is different.
b)The Works is to be completed withir~90 calendar days>rom and
including the Date of Commencement of the Works."-
c)Working hours shall follow the relevant clauses stated in the
Scope of Work. The contractor shall allow everything necessary including overnight and overtime work to comply with such working hours restriction and no claim for extra time or cost shall be raised in this respect.
d)The Project Manager will issue a Certificate of Practical
Completion upon the satisfactory completion of the Works.
4)LIQUIDATED AND ASCERTAINED DAMAGES
Liquidated and Ascertained Damages in the amount of HK$20,000.00 per calendar day for non-completion of the Works within the time for completion as stated in Clause 3 shall be applied to this Contract.
5) PAYMENT(付款)
a)Payment terms shall be follow as below
Upon Countersigning the Letter of Award : 0%