当前位置:文档之家› 电气施工合同(中英文)

电气施工合同(中英文)

电气施工合同(中英文)

电气安装施工合同

Electrical installation construction contract

甲方:

Party A:

乙方:

Party B:

双方同意按下列条款签订合同:

Party A and Party B agreed to sign a contract according to the following terms and

conditions:

1.工程概况:喷漆处理线配套供电设备

Project profile: Spray paint processing line matching power supply unit

工程名称:

Project name:project

工程地点:

Project location:

工程开工日期:

Project Commencement Date:

工程竣工日期:

Project Ccompletion Date:

2.合同内容:该项目安装设备包括:3台高压柜,1台1600kVA变压器,8台低压开关

柜,计量用互感器和计量装置。乙方负责该项目所有设备、电缆、桥架和计量装置

等的电力部分的安装施工和检验工作。施工完成后,乙方负责本项目所有电力公司

的相关报验、通电申请、安装验收、试验和最后通电工作。本项目为全套的交钥匙

工程。本合同价格含以上全部费用(除电力部门指定由业主自己交费项目外)

The content of contract:The project equipment installation including 3 set of

high-voltage switch cabinet,one 1600 kva transformer, 8 sets of low-voltage switch cabinet,

mutual inductor used metering and metering device. Party b is responsible for installation

and inspection of power part of all equipment, electric cable, bridge and metering device

Buyer signed by: Seller signed by:

etc.about this project.Party B is responsible for all inspection

electricity application、installation acceptance、test and the finally electricity work

related to electric power company about this project.this project is full set of turnkey

project.This contract price and above all charges.(In addition to the electric power

department designated by the owner their own to pay.)

3.合同款: 美元

Project Funds: USD (Say only)

4.承包方式:合同签订后,预付款收到后50天完成全部安装工作,55天时办理完项目

验收工作。预付款收到后60-65天时保证正常通电。

Contracting type:After the contract signed,after the advance payment is received

Party B will finish all the installed work in 50 days and have acceptance work of

project transacted in 55 days. Party B make sure that all the equipment will be

normally electrified in 60-65 days when the advance payment is received.

5. 付款条件(Conditions of Payment):

1.合同签订后,预付50%即元人民币。

After the contract signed, prepay 50% of Project Funds which is ¥(RMB).

2.项目通电验收后预付40%即元人民币。

After electrified acceptance work of project finished prepay 40% of Project Funds

which is ¥(RMB).

3.通电验收后6个月时付清剩余10%即元人民币。

Pay off the surplus 10% of Project Funds when electrified acceptance have finished 6

months which is ¥(RMB).

6.甲方责任(Responsibility of TheBuyer):

1.甲方全面负责安装施工现场的管理工作。

Party A is broadly responsible for the management of the installed construction site.

2.开工前3天,甲方应为乙方入场施工创造条件,腾空场地、接通施工水电;水电免费

提供给乙方。

In the three days before Project Commencement Date、Party A should Creat the

conditions for Party B to entrance for construction、empty space、get water and

electricity through which are Party A free offer.

3.开工前10天,甲方应为乙方提供已确定的设计方案图及安装施工清单,审查乙方的分

项工程施工方案,确定工程范围。

In the ten days before Project Commencement Date,Party A should provide the

Buyer signed by: Seller signed by:

相关主题